All Exams Test series for 1 year @ ₹349 only
Question

A can complete a task in $30\text{ days}$, and B can complete the same task in $40\text{ days}$. They work together for $10\text{ days}$, and then C joins them and completes the remaining work in $5\text{ days}$. How long will C alone take to complete the task?

This question was previously asked in
SSC CGL 2025 Tier 2 Paper 1 Question Paper (19-Jan-2026)
The correct answer is
$40\text{ days}$

Work Rate Problem: Calculating C's Task Time

This solution outlines the steps to find how long C alone takes to complete a task, given the work rates of A and B and their combined effort.

Work Rates: A and B Individual Task Time

  • A's daily rate: $\frac{1}{30}$ of the task.
  • B's daily rate: $\frac{1}{40}$ of the task.

Combined Work Rate: A and B Together

The combined daily rate for A and B is:

$ \text{Rate}_{A+B} = \frac{1}{30} + \frac{1}{40} = \frac{4+3}{120} = \frac{7}{120} \text{ task/day} $

Work done by A and B in $10$ days:

$ \text{Work}_{A+B, 10 \text{ days}} = 10 \times \frac{7}{120} = \frac{7}{12} \text{ task} $

Remaining Work Calculation

The work remaining after A and B worked for 10 days is:

$ \text{Remaining Work} = 1 - \frac{7}{12} = \frac{5}{12} \text{ task} $

C completes this $\frac{5}{12}$ of the task in $5$ days.

C's Work Rate Determination

C's daily work rate is calculated as:

$ \text{Rate}_C = \frac{\text{Remaining Work}}{\text{Time}} = \frac{5/12 \text{ task}}{5 \text{ days}} = \frac{1}{12} \text{ task/day} $

C's Total Task Time Calculation

The total time C requires alone to complete the entire task (1 task) is:

$ \text{Time}_C = \frac{1}{\text{Rate}_C} = \frac{1}{1/12} = 12 \text{ days} $

Based on the calculations, C alone takes $12\text{ days}$ to complete the task.

Was this answer helpful?

Similar Questions

  1. Sameer can complete a work in 16 days. In how many days will the work be completed by Ajay, if his efficiency is 60% more than that of Sameer?
  2. 20 women can do work in 16 days. 10 men can complete the same work in 12 days. What is the ratio between the efficiency of a man and a woman?

  3. A and B can complete a task in 12 days together. A is 25% more efficient than B. What percentage of the work is done by A alone?

  4. The efficiency of A, B and C is 2 : 3 : 5. A alone can complete the work in 40 days. They all worked together for 5 days and then C left the work. In how many days can A and B together complete the remaining work?

Important Questions from Work Efficiency

  1. Sumi can complete a job working 5 hours per day in 2 days. If she doubles her working hours per day, then in how many days will she complete the work?

  2. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  3. A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?

  4. 24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?

  5. 3 men working 7 hours a day can complete a piece of work in 45 days. In how many days will 9 men working 6 hours a day complete the same work?

Need Expert Advice?
Upcoming Exams
SSC JHT
September 13, 2026
SSC Selection Post
September 16, 2026
SSC CGL
September 30, 2026
UPSSSC PET
October 23, 2026
Test Series
SSC CGL img
SSC
SSC CGL (Tier I + Tier II) 2026 Mock Test Series - Latest Pattern
2503 Tests 6 Tests Free
4578 Attempts
4.2(852)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App