This solution outlines the steps to find how long C alone takes to complete a task, given the work rates of A and B and their combined effort.
The combined daily rate for A and B is:
$ \text{Rate}_{A+B} = \frac{1}{30} + \frac{1}{40} = \frac{4+3}{120} = \frac{7}{120} \text{ task/day} $
Work done by A and B in $10$ days:
$ \text{Work}_{A+B, 10 \text{ days}} = 10 \times \frac{7}{120} = \frac{7}{12} \text{ task} $
The work remaining after A and B worked for 10 days is:
$ \text{Remaining Work} = 1 - \frac{7}{12} = \frac{5}{12} \text{ task} $
C completes this $\frac{5}{12}$ of the task in $5$ days.
C's daily work rate is calculated as:
$ \text{Rate}_C = \frac{\text{Remaining Work}}{\text{Time}} = \frac{5/12 \text{ task}}{5 \text{ days}} = \frac{1}{12} \text{ task/day} $
The total time C requires alone to complete the entire task (1 task) is:
$ \text{Time}_C = \frac{1}{\text{Rate}_C} = \frac{1}{1/12} = 12 \text{ days} $
Based on the calculations, C alone takes $12\text{ days}$ to complete the task.
20 women can do work in 16 days. 10 men can complete the same work in 12 days. What is the ratio between the efficiency of a man and a woman?
A and B can complete a task in 12 days together. A is 25% more efficient than B. What percentage of the work is done by A alone?
Sumi can complete a job working 5 hours per day in 2 days. If she doubles her working hours per day, then in how many days will she complete the work?
Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?
24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?
3 men working 7 hours a day can complete a piece of work in 45 days. In how many days will 9 men working 6 hours a day complete the same work?