This solution outlines the steps to find how long C alone takes to complete a task, given the work rates of A and B and their combined effort.
The combined daily rate for A and B is:
$ \text{Rate}_{A+B} = \frac{1}{30} + \frac{1}{40} = \frac{4+3}{120} = \frac{7}{120} \text{ task/day} $
Work done by A and B in $10$ days:
$ \text{Work}_{A+B, 10 \text{ days}} = 10 \times \frac{7}{120} = \frac{7}{12} \text{ task} $
The work remaining after A and B worked for 10 days is:
$ \text{Remaining Work} = 1 - \frac{7}{12} = \frac{5}{12} \text{ task} $
C completes this $\frac{5}{12}$ of the task in $5$ days.
C's daily work rate is calculated as:
$ \text{Rate}_C = \frac{\text{Remaining Work}}{\text{Time}} = \frac{5/12 \text{ task}}{5 \text{ days}} = \frac{1}{12} \text{ task/day} $
The total time C requires alone to complete the entire task (1 task) is:
$ \text{Time}_C = \frac{1}{\text{Rate}_C} = \frac{1}{1/12} = 12 \text{ days} $
Based on the calculations, C alone takes $12\text{ days}$ to complete the task.
20 women can do work in 16 days. 10 men can complete the same work in 12 days. What is the ratio between the efficiency of a man and a woman?
A and B can complete a task in 12 days together. A is 25% more efficient than B. What percentage of the work is done by A alone?
A and B together can complete a certain work in 20 days whereas B and C together can complete it in 24 days. If A is twice as good a workman as C, then in what time will B alone do 40% of the same work?
14 men can complete a work in 15 days. If 21 men are employed, then in how many days will they complete the same work?
A can do a certain work in 15 days, while B can do the same work in 21 days. If they work together, then in how many days will the same work be completed?
To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in \(11 \frac{1}{3}\) days, then B alone can complete \(\rm \frac{7}{9}^{th}\) part of the original work in:
Two men and 7 women can complete a work in 28 days whereas 6 men and 16 women can do the same work in 11 days. In how many days can 7 men complete the same work?