A and B can complete a task in 12 days together. A is 25% more efficient than B. What percentage of the work is done by A alone?

This question was previously asked in
SSC CGL 2025 Tier 2 Paper 1 Question Paper (19-Jan-2026)
The correct answer is

55.56%

Since A is 25% more efficient than B, the ratio of their efficiencies is \(A:B = 125:100 = 5:4\).

Let A's daily work rate be \(5k\) and B's be \(4k\), so their combined rate is \(9k\) per day.

Together they complete the work in 12 days, so \(9k \times 12 = 1\) (total work), giving \(k = \frac{1}{108}\).

The percentage of work done by A alone (out of the combined work) is \(\frac{5k}{9k} \times 100 = \frac{5}{9} \times 100\).

Calculating, \(\frac{5}{9} \times 100 = 55.56\%\).

Hence, the answer is 55.56%.

Was this answer helpful?

Similar Questions

  1. A can complete a task in $30\text{ days}$, and B can complete the same task in $40\text{ days}$. They work together for $10\text{ days}$, and then C joins them and completes the remaining work in $5\text{ days}$. How long will C alone take to complete the task?
  2. The efficiency of A, B and C is 2 : 3 : 5. A alone can complete the work in 40 days. They all worked together for 5 days and then C left the work. In how many days can A and B together complete the remaining work?
  3. 20 women can do work in 16 days. 10 men can complete the same work in 12 days. What is the ratio between the efficiency of a man and a woman?

  4. Sameer can complete a work in 16 days. In how many days will the work be completed by Ajay, if his efficiency is 60% more than that of Sameer?

Important Questions from Work Efficiency

  1. A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?

  2. 24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?

  3. A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-

  4. A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?

  5. A is thrice as good a workman as B. C alone takes 48 days to paint a house. All three A, B and C working together take 16 days to paint the house. It will take how many days for A alone to paint the house?

Need Expert Advice?
Upcoming Exams
SSC JE
November 02, 2026
SSC CPO
November 23, 2026
SSC CHSL
November 30, 2026
Test Series
SSC CGL img
SSC
SSC CGL (Tier I + Tier II) 2026 Mock Test Series - Latest Pattern
2509 Tests 6 Tests Free
8792 Attempts
4.2(941)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App