Question

What is the purpose of a pre-molded joint in underground cables?

This question was previously asked in
RRB NTPC 2025 Graduate Level CBT 1 Question Paper (25-Mar-2026) (Shift 3)
The correct answer is

To securely connect two or more cables

A cable joint exists to restore both the conductor path and the insulation where two cable lengths must be brought together in a run, and a pre-molded joint achieves this with factory-made insulating components.

The pre-molded insulating body is manufactured to precise dimensions and slipped over the prepared meeting point of the cable ends, so the stress control and insulation are consistent and reliable.

Its purpose is to make a sound mechanical and electrical connection between two or more cable conductors while rebuilding continuous insulation across the join, so the underground cable behaves as one.

Terminating a cable at equipment is done by a cable termination or gland, not a joint, so that option names a different fitting.

Regulating cable voltage is a function of transformers and regulators, something a passive joint cannot do.

Merely insulating a single cut end is only part of the story; the defining role of a joint is to connect cables together, which the insulation then covers.

Hence, the answer is To securely connect two or more cables.

Was this answer helpful?

Similar Questions

  1. In which situation is DC transmission preferred over AC transmission in power networks?

  2. What is the purpose of the Cable Sheath Continuity Test in underground cables?

  3. Which of the following methods is used to detect an oil leak in an underground oil filled cable joint without excavation?

  4. While repairing overhead transmission lines, which type of wire joint is most suitable for joining two stranded conductors with high current carrying requirements?

  5. Which of the following equipment provides surge protection in substations?

  6. Choose the correct sequence for erecting an overhead transmission line.

     1. Foundation work 

    2. Tower erection 

    3. Conductor stringing 

    4. Insulator installation

  7. Which type of substation would be strategically installed on a high-voltage transmission line to improve network reliability by isolating faults without changing voltage levels?

  8. Which of the following steps helps prevent void formation during epoxy resin casting in underground cable joints?

  9. A technician is using the Murray loop test to locate a ground fault in a two-core cable. Which essential component must be connected to complete the test setup?


Important Questions from Transmission and Distribution

  1. For household wiring and small units, the following should be used as a safety measure:

  2. The minimum clearance distance that equipment should be kept away from 50 kV power lines is:

  3. What is the purpose of a lighting arrester connected between the line and earth in a power S/M?

  4. From the given options, identify the type of lug used for connecting an aluminum cable to a copper bus bar.

  5. What is the color of neutral in three core flexible cables?

Need Expert Advice?
Upcoming Exams
RRB NTPC
September 27, 2026
Test Series
RRB ALP img
Railways
RRB ALP 2026 Mock Test series
1035 Tests 1 Tests Free
741 Attempts
4.3(233)
English, Hindi
More Questions from RRB ALP

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App