In CRC based design, a CRC Team consists of : (a) one or two users representatives (b) several programmers (c) project co-ordinators (d) one or two system analysts Codes :
(a), (c) and (d)
CRC (Class-Responsibility-Collaborator) modelling is done in a session where the team role-plays scenarios using index cards.
The team is kept small: one or two user representatives who know the domain, one or two system analysts, and a project co-ordinator who facilitates the session.
Programmers are not part of the core CRC team because the activity is about analysis of responsibilities, not coding.
Hence, (a), (c) and (d).
To compute function points (FP), the following relationship is used
FP = Count – total × (0.65 + 0.01 × Σ(Fi)) where Fi (i = 1 to n) are value adjustment factors (VAF) based on n questions. The value of n is
Which one of the following statements, related to the requirements phase in Software Engineering, is incorrect ?
Which one of the following non-functional quality attributes is not highly affected by the architecture of the software ?
Requirements prioritisation and negotiation belongs to :
Match the following :
| (a) Size-oriented metrics | (i) uses number of external interfaces as one of the measurement parameter. |
| (b) Function-oriented metrics | (ii) originally designed to be applied to business information systems. |
| (c) Extended Function Point metrics | (iii) derived by normalizing quality and/or productivity measures by considering the size of the software. |
| (d) Function point | (iv) uses algorithm characteristics as one of the measurement parameter. |
Codes :
Match the following :
| List - I | List - II |
| a. Correctness | i. The extent to which a software tolerates the unexpected problems |
| b. Accuracy | ii. The extent to which a software meets its specifications |
| c. Robustness | iii. The extent to which a software has specified functions |
| d. Completeness | iv. Meeting specifications with precision |
Consider a project with the following functional units :
Number of user inputs = 50
Number of user outputs = 40
Number of user enquiries = 35
Number of user files = 06
Number of external interfaces = 04
Assuming all complexity adjustment factors and weighing factors as average, the function points for the project will be
In function point analysis, the number of complexity adjustment factors is
Which one of the following is not the part of requirement management?
Collaborative document inspection technique used for?
What is the other name of Data Flow Diagram (DFD)?
The process followed in order to find difficult, unknown and hidden information about a software system is called