According to IS 1892:2021, for a compact building site of about 0.4 hectare area, what is the recommended minimum number and location of boreholes or test pits for soil investigation?
One borehole or test pit at each corner and one at the center
The problem requires understanding the guidelines for soil investigation on a compact building site, as per IS 1892:2021 (Code of Practice for Subsurface Investigation for Foundations).
According to IS 1892:2021, the recommended practice for soil investigation involves a strategic placement of boreholes or test pits to adequately assess soil conditions. The guidelines typically suggest that for small sites, like the one in question (0.4 hectare), the boreholes or test pits should be spaced in a manner that captures variability in soil properties across the site.
For a compact site of about 0.4 hectare, it is recommended to:
Reviewing the given options:
Therefore, based on IS 1892:2021, the most suitable strategy for soil investigation on a 0.4 hectare compact building site is to have one borehole or test pit at each corner and one at the center. This option provides a comprehensive evaluation of the site, capturing potential variations in soil conditions effectively.
Which method is primarily used to fill cracks, voids, and fissures in loose gravels and rocky strata?
What is the primary purpose of pressure grouting in building foundation treatment work?
In order to minimize sampling disturbance the area ratio A r,\(\left( {{{\rm{A}}_{\rm{r}}} = \frac{{{\rm{D}}_{\rm{e}}^2 - {\rm{D}}_{\rm{i}}^2}}{{{\rm{D}}_{\rm{i}}^2}}{\rm{\;}}} \right)\) should be
Shelby tube is one of the most widely used devices for:
Which one of the following is NOT a soil exploration technique?
If the sampler tube is pushed at the bottom of the bore hole to a distance of 585 mm with length of the sample recovered being 535 mm. Then the value of recovery ratio is ______.
If the inside diameters of the cutting edge and sample tube are 68 mm & 70 mm respectively and 76 mm & 74 mm are the outside diameters of the cutting edge and sample tube respectively, then outside clearance of the sampler is _______.