All Exams Test series for 1 year @ ₹349 only
Question

A work when done by 10 women is completed in 12 days. The same work can be completed in 8 days by 5 men. How many days will it take to complete when 6 women and 3 men are employed to perform the same job?

This question was previously asked in
CDS I 2018 Elementary Mathematics Previous Year Paper (04-Feb-2018)
The correct answer is

8

Understanding Work and Time Problems

Work and Time problems often involve calculating how long it takes individuals or groups to complete a task based on their work rates. The fundamental principle is that if someone completes a work in 'n' days, their work rate per day is \(\frac{1}{n}\) of the total work. When multiple people work together, their individual work rates are added to find the combined work rate.

Calculating Individual Work Rates

We are given the following information:

  • 10 women can complete the work in 12 days.
  • 5 men can complete the same work in 8 days.

Let's find the work rate of one woman and one man per day.

  1. Work rate of 10 women: If 10 women complete the work in 12 days, the total work done by 10 women in one day is \(\frac{1}{12}\) of the total work.
  2. Work rate of 1 woman: To find the work rate of a single woman, we divide the work rate of 10 women by 10.
    Work rate of 1 woman per day \(= \frac{1}{12} \div 10 = \frac{1}{12} \times \frac{1}{10} = \frac{1}{120}\) of the total work.
  3. Work rate of 5 men: If 5 men complete the work in 8 days, the total work done by 5 men in one day is \(\frac{1}{8}\) of the total work.
  4. Work rate of 1 man: To find the work rate of a single man, we divide the work rate of 5 men by 5.
    Work rate of 1 man per day \(= \frac{1}{8} \div 5 = \frac{1}{8} \times \frac{1}{5} = \frac{1}{40}\) of the total work.

So, a woman completes \(\frac{1}{120}\) of the work per day, and a man completes \(\frac{1}{40}\) of the work per day.

Calculating Combined Work Rate

Now, we need to find out how many days it will take for 6 women and 3 men to complete the job when working together. First, we calculate their combined work rate per day.

  1. Work done by 6 women in one day: This is 6 times the work rate of one woman.
    Work by 6 women per day \(= 6 \times \frac{1}{120} = \frac{6}{120} = \frac{1}{20}\) of the total work.
  2. Work done by 3 men in one day: This is 3 times the work rate of one man.
    Work by 3 men per day \(= 3 \times \frac{1}{40} = \frac{3}{40}\) of the total work.
  3. Combined work rate of 6 women and 3 men: Add the work done by 6 women and 3 men in one day.
    Combined work rate per day \(= (\text{Work by 6 women}) + (\text{Work by 3 men})\)
    Combined work rate per day \(= \frac{1}{20} + \frac{3}{40}\)

To add these fractions, we find a common denominator, which is 40.

\(\frac{1}{20} = \frac{1 \times 2}{20 \times 2} = \frac{2}{40}\)

So, the combined work rate per day \(= \frac{2}{40} + \frac{3}{40} = \frac{2 + 3}{40} = \frac{5}{40}\)

This fraction can be simplified:

Combined work rate per day \(= \frac{5}{40} = \frac{1}{8}\) of the total work.

Determining Time Taken

If 6 women and 3 men together complete \(\frac{1}{8}\) of the total work in one day, the total number of days required to complete the entire work (which is 1 unit of work) is the reciprocal of their combined work rate.

Time taken \(= \frac{\text{Total Work}}{\text{Combined Work Rate per Day}}\)

Time taken \(= \frac{1}{\frac{1}{8}} = 1 \times 8 = 8\) days.

Therefore, it will take 8 days for 6 women and 3 men to complete the same job.

Summary of Calculations

Group Time Taken (days) Total Work per Day Work Rate per Person per Day
10 Women 12 \(\frac{1}{12}\) \(\frac{1}{120}\) (per woman)
5 Men 8 \(\frac{1}{8}\) \(\frac{1}{40}\) (per man)
6 Women - \(6 \times \frac{1}{120} = \frac{1}{20}\) -
3 Men - \(3 \times \frac{1}{40} = \frac{3}{40}\) -
6 Women + 3 Men ? \(\frac{1}{20} + \frac{3}{40} = \frac{1}{8}\) -

Since the combined work rate is \(\frac{1}{8}\) of the work per day, they will complete the work in 8 days.

Revision Table: Key Concepts in Work and Time

Concept Explanation Formula
Work Rate The amount of work done by a person or group in a unit of time (e.g., per day, per hour). Work Rate \(= \frac{\text{Total Work}}{\text{Time Taken}}\)
Time Taken The total time required to complete a certain amount of work. Time Taken \(= \frac{\text{Total Work}}{\text{Work Rate}}\)
Combined Work Rate The sum of individual work rates when multiple people or groups work together. Combined Work Rate \(= \text{Rate}_1 + \text{Rate}_2 + \text{Rate}_3 + ...\)
Total Work Often considered as 1 unit of work for calculation purposes. Total Work \(= \text{Work Rate} \times \text{Time Taken}\)

Additional Information: Efficiency and Inverse Relationship

Work and time problems often involve the concept of efficiency. Efficiency is directly proportional to the work rate. A more efficient person does more work in the same amount of time or completes the same work in less time.

There is an inverse relationship between the number of workers and the time taken to complete a job, assuming all workers have the same efficiency. If you increase the number of workers, the time taken to complete the same amount of work decreases. Similarly, time taken is inversely proportional to the work rate.

In this problem, we first found the individual work rates based on the given group rates and times. Then, we used these individual rates to find the combined rate of the new group (6 women and 3 men) and finally calculated the time required.

Was this answer helpful?

Similar Questions

  1. A man undertakes to do a work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time?

  2. 30 men can complete a job in 40 days. However, after 24 days some men left the job. The remaining people took another 40 days to complete the job. The number of men who left the job is


Important Questions from Work and Wages

  1. A can complete a work alone in 8 days. B can complete the same work alone in 12 days. C alone complete the same work in 16 days. They complete the work in 3 days with the help of D. If they get Rs.12000 for the work, then how much money does the D get?

  2. If 15 men can complete a work in 16 days by working 8 hours daily, then in how many days will 10 men complete the work by working 12 hours daily?

  3. 10 men working 8 hours a day can finish a work in 28 days. In how many days, 8 men working 5 hours a day with complete 50% of that work?

  4. A can do a work in 12 days and B in 16 days. They undertook to do it for Rs. 6000 with the help of ‘C’ they completed the work in 6 days. What is the share of A?

  5. Twenty lamps can be lighted for 6 hr a day for 20 days at a cost of Rs. 100. How much would be the cost of lighting 40 lamps, 8 hr for 12 days?

Need Expert Advice?
Upcoming Exams
NDA
September 13, 2026
CDS
September 13, 2026
Test Series
CDS img
Defence
UPSC CDS 2026 Mock Test Series
540 Tests 4 Tests Free
1283 Attempts
4.3(170)
English, Hindi
More Questions from CDS

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App