All Exams Test series for 1 year @ ₹349 only
Question

A man undertakes to do a work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time?

The correct answer is

100

Solving Work and Time Problems: Finding Additional Men

This problem is about how the amount of work done relates to the number of men working and the time they spend. We are given a situation where a task needs to be completed within a specific timeframe, and we need to figure out how to adjust the workforce to meet the deadline after a certain amount of work has been done.

Understanding the Relationship

The core idea behind these types of problems is that the total "work effort" required to complete a task is constant. Work effort can be thought of as the product of the number of workers, the time they work, and their efficiency. Assuming efficiency remains constant, the total work effort is proportional to (Number of Men) \(\times\) (Number of Days).

If the work done is also considered, the relationship can be expressed as:

\[ \frac{M_1 \times D_1}{W_1} = \frac{M_2 \times D_2}{W_2} \] Where:

  • \(M_1\) = Initial number of men
  • \(D_1\) = Initial number of days
  • \(W_1\) = Amount of work done in the initial phase
  • \(M_2\) = Number of men required for the second phase
  • \(D_2\) = Number of days for the second phase
  • \(W_2\) = Amount of work to be done in the second phase

Applying the Formula to the Problem

Let's break down the information given in the problem:

  • Total time allowed for the work = 150 days.
  • Initial number of men employed = 200 men.
  • Time spent in the first phase = 50 days.
  • Work done in the first phase = A quarter of the total work, which is \( \frac{1}{4} \).

Now, let's determine the details for the second phase:

  • Remaining time to complete the work = Total time - Time spent = 150 days - 50 days = 100 days.
  • Remaining work to be done = Total work - Work done = \( 1 - \frac{1}{4} = \frac{3}{4} \).
  • Let \(M_2\) be the total number of men required to complete the remaining work in the remaining time.

Using the formula \( \frac{M_1 \times D_1}{W_1} = \frac{M_2 \times D_2}{W_2} \), we can plug in the values:

\[ \frac{200 \times 50}{\frac{1}{4}} = \frac{M_2 \times 100}{\frac{3}{4}} \]

Let's solve for \(M_2\):

\[ \frac{200 \times 50}{\frac{1}{4}} = 200 \times 50 \times 4 = 40000 \]

\[ \frac{M_2 \times 100}{\frac{3}{4}} = M_2 \times 100 \times \frac{4}{3} = M_2 \times \frac{400}{3} \]

So, the equation becomes:

\[ 40000 = M_2 \times \frac{400}{3} \]

To find \(M_2\), we rearrange the equation:

\[ M_2 = 40000 \times \frac{3}{400} \]

\[ M_2 = \frac{40000 \times 3}{400} = \frac{100 \times 3 \times 400}{400} = 100 \times 3 \]

\[ M_2 = 300 \]

This means a total of 300 men are needed for the remaining 100 days to finish the work on time.

Calculating Additional Men

The question asks for the number of additional men required. The initial number of men was 200. The total number of men needed for the rest of the project is 300.

Additional men = Total men needed - Initial men

Additional men = 300 - 200 = 100 men.

Therefore, 100 additional men should be employed to ensure the whole work is finished within the original 150-day deadline.

Summary of Steps

  1. Identify the initial conditions (Men, Days, Work Done).
  2. Identify the target conditions (Remaining Days, Remaining Work).
  3. Use the man-days-work relationship formula: \( \frac{M_1 \times D_1}{W_1} = \frac{M_2 \times D_2}{W_2} \).
  4. Solve for the required number of men (\(M_2\)) for the second phase.
  5. Calculate the additional men needed by subtracting the initial number of men from \(M_2\).
Phase Men (M) Days (D) Work (W)
Phase 1 (Given) 200 50 \(\frac{1}{4}\)
Phase 2 (Required) \(M_2\) (to find) 100 \(\frac{3}{4}\)

Revision Table: Key Concepts in Work and Time

Concept Explanation Formula/Relationship
Work Rate Amount of work done per unit of time by one person/unit. Work = Rate \(\times\) Time
Man-Days A unit representing the amount of work one man can do in one day. Total work is often measured in man-days. Total Work = Number of Men \(\times\) Number of Days (assuming constant rate)
Inverse Proportion If the number of men increases, the time taken to complete the same amount of work decreases (assuming constant rate). \( M_1 \times D_1 = M_2 \times D_2 \) (for same work W)
Direct Proportion If the amount of work increases, the time taken or the number of men required increases (assuming other factors are constant). \( \frac{W_1}{D_1} = \frac{W_2}{D_2} \) (for same men M) or \( \frac{W_1}{M_1} = \frac{W_2}{M_2} \) (for same days D)

Additional Information: Work and Time Problem Variations

Work and time problems can come in various forms, including:

  • Problems involving individual work rates and combined work rates of multiple people.
  • Problems where efficiency varies between workers.
  • Problems involving pipes and cisterns (where filling/emptying is the "work").
  • Problems where some workers leave or join during the task.

The key to solving these problems is often to first determine the total amount of work (sometimes in "units" or "man-days") or the individual rates, and then calculate how much work is done or needs to be done under different conditions. The formula \( \frac{M_1 \times D_1}{W_1} = \frac{M_2 \times D_2}{W_2} \) is a powerful tool for problems involving changes in the number of workers and time for a given amount of work.

Was this answer helpful?

Important Questions from Work and Wages

  1. A and B worked together and received a total of Rs. 18,000 for 15 days. A's efficiency in the work was 5 times that of B's. The daily wage of A (in Rs.) was:

  2. Samir and Puneet can complete the same work in 10 days and 15 days respectively. The work was assigned for Rs.4500. After working together for 3 days Samir and Puneet involved Ashok. The work was completed in total 5 days. What amount (in Rs.) was paid to Ashok?

  3. 5 women and 9 girls earn a total of ₹18,720 in 9 days, while 9 women and 16 girls earn a total of ₹ 52,080 in 14 days. How much will 12 women and 7 girls together earn (in ₹) in 13 days?

  4. X, Y and Z completed a work costing Rs. 3,400, X worked for 5 days, Y for 7 days and Z for 10 days. If their daily wages are in the ratio of 4 ∶ 5 ∶ 3, how much amount will be received by X?

  5. A,B and C can do a work in 10 days, 15 days, and 20 days, respectively. They finished that work together and got Rs. 2,600 as wages. Find C's wage.

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App