All Exams Test series for 1 year @ ₹349 only
Question

A man undertakes to do a work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time?

This question was previously asked in
CDS I 2018 Elementary Mathematics Previous Year Paper (04-Feb-2018)
The correct answer is

100

Solving Work and Time Problems: Finding Additional Men

This problem is about how the amount of work done relates to the number of men working and the time they spend. We are given a situation where a task needs to be completed within a specific timeframe, and we need to figure out how to adjust the workforce to meet the deadline after a certain amount of work has been done.

Understanding the Relationship

The core idea behind these types of problems is that the total "work effort" required to complete a task is constant. Work effort can be thought of as the product of the number of workers, the time they work, and their efficiency. Assuming efficiency remains constant, the total work effort is proportional to (Number of Men) \(\times\) (Number of Days).

If the work done is also considered, the relationship can be expressed as:

\[ \frac{M_1 \times D_1}{W_1} = \frac{M_2 \times D_2}{W_2} \] Where:

  • \(M_1\) = Initial number of men
  • \(D_1\) = Initial number of days
  • \(W_1\) = Amount of work done in the initial phase
  • \(M_2\) = Number of men required for the second phase
  • \(D_2\) = Number of days for the second phase
  • \(W_2\) = Amount of work to be done in the second phase

Applying the Formula to the Problem

Let's break down the information given in the problem:

  • Total time allowed for the work = 150 days.
  • Initial number of men employed = 200 men.
  • Time spent in the first phase = 50 days.
  • Work done in the first phase = A quarter of the total work, which is \( \frac{1}{4} \).

Now, let's determine the details for the second phase:

  • Remaining time to complete the work = Total time - Time spent = 150 days - 50 days = 100 days.
  • Remaining work to be done = Total work - Work done = \( 1 - \frac{1}{4} = \frac{3}{4} \).
  • Let \(M_2\) be the total number of men required to complete the remaining work in the remaining time.

Using the formula \( \frac{M_1 \times D_1}{W_1} = \frac{M_2 \times D_2}{W_2} \), we can plug in the values:

\[ \frac{200 \times 50}{\frac{1}{4}} = \frac{M_2 \times 100}{\frac{3}{4}} \]

Let's solve for \(M_2\):

\[ \frac{200 \times 50}{\frac{1}{4}} = 200 \times 50 \times 4 = 40000 \]

\[ \frac{M_2 \times 100}{\frac{3}{4}} = M_2 \times 100 \times \frac{4}{3} = M_2 \times \frac{400}{3} \]

So, the equation becomes:

\[ 40000 = M_2 \times \frac{400}{3} \]

To find \(M_2\), we rearrange the equation:

\[ M_2 = 40000 \times \frac{3}{400} \]

\[ M_2 = \frac{40000 \times 3}{400} = \frac{100 \times 3 \times 400}{400} = 100 \times 3 \]

\[ M_2 = 300 \]

This means a total of 300 men are needed for the remaining 100 days to finish the work on time.

Calculating Additional Men

The question asks for the number of additional men required. The initial number of men was 200. The total number of men needed for the rest of the project is 300.

Additional men = Total men needed - Initial men

Additional men = 300 - 200 = 100 men.

Therefore, 100 additional men should be employed to ensure the whole work is finished within the original 150-day deadline.

Summary of Steps

  1. Identify the initial conditions (Men, Days, Work Done).
  2. Identify the target conditions (Remaining Days, Remaining Work).
  3. Use the man-days-work relationship formula: \( \frac{M_1 \times D_1}{W_1} = \frac{M_2 \times D_2}{W_2} \).
  4. Solve for the required number of men (\(M_2\)) for the second phase.
  5. Calculate the additional men needed by subtracting the initial number of men from \(M_2\).
Phase Men (M) Days (D) Work (W)
Phase 1 (Given) 200 50 \(\frac{1}{4}\)
Phase 2 (Required) \(M_2\) (to find) 100 \(\frac{3}{4}\)

Revision Table: Key Concepts in Work and Time

Concept Explanation Formula/Relationship
Work Rate Amount of work done per unit of time by one person/unit. Work = Rate \(\times\) Time
Man-Days A unit representing the amount of work one man can do in one day. Total work is often measured in man-days. Total Work = Number of Men \(\times\) Number of Days (assuming constant rate)
Inverse Proportion If the number of men increases, the time taken to complete the same amount of work decreases (assuming constant rate). \( M_1 \times D_1 = M_2 \times D_2 \) (for same work W)
Direct Proportion If the amount of work increases, the time taken or the number of men required increases (assuming other factors are constant). \( \frac{W_1}{D_1} = \frac{W_2}{D_2} \) (for same men M) or \( \frac{W_1}{M_1} = \frac{W_2}{M_2} \) (for same days D)

Additional Information: Work and Time Problem Variations

Work and time problems can come in various forms, including:

  • Problems involving individual work rates and combined work rates of multiple people.
  • Problems where efficiency varies between workers.
  • Problems involving pipes and cisterns (where filling/emptying is the "work").
  • Problems where some workers leave or join during the task.

The key to solving these problems is often to first determine the total amount of work (sometimes in "units" or "man-days") or the individual rates, and then calculate how much work is done or needs to be done under different conditions. The formula \( \frac{M_1 \times D_1}{W_1} = \frac{M_2 \times D_2}{W_2} \) is a powerful tool for problems involving changes in the number of workers and time for a given amount of work.

Was this answer helpful?

Similar Questions

  1. A work when done by 10 women is completed in 12 days. The same work can be completed in 8 days by 5 men. How many days will it take to complete when 6 women and 3 men are employed to perform the same job?

  2. 30 men can complete a job in 40 days. However, after 24 days some men left the job. The remaining people took another 40 days to complete the job. The number of men who left the job is


Important Questions from Work and Wages

  1. Which among the following are true about wages?

    A. The fair wage was something between minimum wage and living wage
    B. The Surplus Value Theory is associated with Maurice Dobb
    C. As per the Wages Fund Theory there exists pre-determined fund for the payment of wages
    D. Living wage provides workers and their families to live on some level considered adequate
    E. According to the "Bargaining Theory" there is an upper and lower limit on wage rates and the actual rates are determined by the capitalist

    Choose the most appropriate answer from the options given below:

  2. A shopkeeper employs a delivery boy and gives him a motorcycle for home delivery. For every delivery, the boy is given ₹ 5. At the end of the day, he also gets ₹ 2 for every kilometre of the distance covered in the day. The boy wants to earn more than ₹ 500 a day, but does not want to travel more than 100 km. Which of the following numbers of deliveries would definitely meet his target?
  3. 18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 15 hours a day?
  4. A building contractor employs 25 skilled workers and 5 unskilled workers. To a skilled worker he pays ₹30 per hour and to an unskilled worker ₹24 per hour. The average wage per hour (in ₹) paid by the contractor is:
  5. A and B can complete a piece of work in 15 days and 10 days respectively. They got a contract to complete the work for Rs. 35000. The share of A (in Rs.) in the contracted money will be:

Need Expert Advice?
Test Series
CDS img
Defence
UPSC CDS 2026 Mock Test Series
559 Tests 4 Tests Free
1821 Attempts
4.3(195)
English, Hindi
More Questions from CDS

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App