30 men can complete a job in 40 days. However, after 24 days some men left the job. The remaining people took another 40 days to complete the job. The number of men who left the job is
18
This problem deals with the concept of work and time, specifically how the number of workers affects the time taken to complete a job. The core idea is that the total amount of work is constant, and it can be measured in 'man-days'. One man working for one day completes one unit of 'man-day' of work.
We are given that 30 men can complete a job in 40 days. The total work required to complete the job can be calculated as the product of the number of men and the number of days they take.
Total Work = Number of Men × Number of Days
Total Work = \(30 \text{ men} \times 40 \text{ days} = 1200 \text{ man-days}\)
So, the entire job requires 1200 man-days of effort.
The problem states that after 24 days, some men left. In the first 24 days, the original 30 men were working. We can calculate the amount of work completed during this period.
Work done in first 24 days = Number of Men × Number of Days worked
Work done in first 24 days = \(30 \text{ men} \times 24 \text{ days} = 720 \text{ man-days}\)
Now we need to find out how much work is left to be done. This is the total work minus the work already completed.
Remaining Work = Total Work - Work done in first 24 days
Remaining Work = \(1200 \text{ man-days} - 720 \text{ man-days} = 480 \text{ man-days}\)
So, 480 man-days of work still need to be completed.
The remaining 480 man-days of work were completed by the remaining men in another 40 days. Let the number of men who remained on the job be \(M_{rem}\).
Remaining Work = Number of Remaining Men × Additional Days taken
\(480 \text{ man-days} = M_{rem} \text{ men} \times 40 \text{ days}\)
We can solve this equation to find \(M_{rem}\):
\(M_{rem} = \frac{480 \text{ man-days}}{40 \text{ days}}\)
\(M_{rem} = 12 \text{ men}\)
So, 12 men remained to complete the rest of the job.
Initially, there were 30 men on the job. After 24 days, some left, and 12 men remained. The number of men who left is the difference between the initial number of men and the number of men who remained.
Number of Men Who Left = Initial Number of Men - Number of Remaining Men
Number of Men Who Left = \(30 \text{ men} - 12 \text{ men} = 18 \text{ men}\)
Therefore, 18 men left the job after 24 days.
| Description | Calculation | Result |
|---|---|---|
| Total Work | \(30 \text{ men} \times 40 \text{ days}\) | \(1200 \text{ man-days}\) |
| Work done in first 24 days | \(30 \text{ men} \times 24 \text{ days}\) | \(720 \text{ man-days}\) |
| Remaining Work | \(1200 \text{ man-days} - 720 \text{ man-days}\) | \(480 \text{ man-days}\) |
| Number of Remaining Men | \(\frac{480 \text{ man-days}}{40 \text{ days}}\) | \(12 \text{ men}\) |
| Number of Men Who Left | \(30 \text{ men} - 12 \text{ men}\) | \(18 \text{ men}\) |
Based on the calculations, the number of men who left the job is 18.
Understanding the relationship between work, men, and time is crucial for these types of problems.
Work and Time problems in quantitative aptitude can come in several forms:
Solving these problems often involves calculating the total work unit (like man-days), the work done in different phases, and then using the remaining work to find the unknown variable (like time or number of workers).
A man undertakes to do a work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time?
A work when done by 10 women is completed in 12 days. The same work can be completed in 8 days by 5 men. How many days will it take to complete when 6 women and 3 men are employed to perform the same job?
Which among the following are true about wages?
A. The fair wage was something between minimum wage and living wage
B. The Surplus Value Theory is associated with Maurice Dobb
C. As per the Wages Fund Theory there exists pre-determined fund for the payment of wages
D. Living wage provides workers and their families to live on some level considered adequate
E. According to the "Bargaining Theory" there is an upper and lower limit on wage rates and the actual rates are determined by the capitalist
Choose the most appropriate answer from the options given below:
A and B can complete a piece of work in 15 days and 10 days respectively. They got a contract to complete the work for Rs. 35000. The share of A (in Rs.) in the contracted money will be: