All Exams Test series for 1 year @ ₹349 only
Question

30 men can complete a job in 40 days. However, after 24 days some men left the job. The remaining people took another 40 days to complete the job. The number of men who left the job is

This question was previously asked in
CDS I 2017 General Knowledge Previous Year Paper (05-Feb-2017)
The correct answer is

18

Solving Work and Time Problems: Men Leaving the Job

This problem deals with the concept of work and time, specifically how the number of workers affects the time taken to complete a job. The core idea is that the total amount of work is constant, and it can be measured in 'man-days'. One man working for one day completes one unit of 'man-day' of work.

Calculating Total Work Units

We are given that 30 men can complete a job in 40 days. The total work required to complete the job can be calculated as the product of the number of men and the number of days they take.

Total Work = Number of Men × Number of Days

Total Work = \(30 \text{ men} \times 40 \text{ days} = 1200 \text{ man-days}\)

So, the entire job requires 1200 man-days of effort.

Work Done Before Men Left

The problem states that after 24 days, some men left. In the first 24 days, the original 30 men were working. We can calculate the amount of work completed during this period.

Work done in first 24 days = Number of Men × Number of Days worked

Work done in first 24 days = \(30 \text{ men} \times 24 \text{ days} = 720 \text{ man-days}\)

Calculating Remaining Work

Now we need to find out how much work is left to be done. This is the total work minus the work already completed.

Remaining Work = Total Work - Work done in first 24 days

Remaining Work = \(1200 \text{ man-days} - 720 \text{ man-days} = 480 \text{ man-days}\)

So, 480 man-days of work still need to be completed.

Finding the Number of Remaining Men

The remaining 480 man-days of work were completed by the remaining men in another 40 days. Let the number of men who remained on the job be \(M_{rem}\).

Remaining Work = Number of Remaining Men × Additional Days taken

\(480 \text{ man-days} = M_{rem} \text{ men} \times 40 \text{ days}\)

We can solve this equation to find \(M_{rem}\):

\(M_{rem} = \frac{480 \text{ man-days}}{40 \text{ days}}\)

\(M_{rem} = 12 \text{ men}\)

So, 12 men remained to complete the rest of the job.

Determining the Number of Men Who Left

Initially, there were 30 men on the job. After 24 days, some left, and 12 men remained. The number of men who left is the difference between the initial number of men and the number of men who remained.

Number of Men Who Left = Initial Number of Men - Number of Remaining Men

Number of Men Who Left = \(30 \text{ men} - 12 \text{ men} = 18 \text{ men}\)

Therefore, 18 men left the job after 24 days.

Description Calculation Result
Total Work \(30 \text{ men} \times 40 \text{ days}\) \(1200 \text{ man-days}\)
Work done in first 24 days \(30 \text{ men} \times 24 \text{ days}\) \(720 \text{ man-days}\)
Remaining Work \(1200 \text{ man-days} - 720 \text{ man-days}\) \(480 \text{ man-days}\)
Number of Remaining Men \(\frac{480 \text{ man-days}}{40 \text{ days}}\) \(12 \text{ men}\)
Number of Men Who Left \(30 \text{ men} - 12 \text{ men}\) \(18 \text{ men}\)

Conclusion

Based on the calculations, the number of men who left the job is 18.

Revision Table: Work and Time Concepts

Understanding the relationship between work, men, and time is crucial for these types of problems.

  • Work Done: Work is often measured in 'man-days' or 'man-hours', representing the total effort needed.
  • Formula: Work = Number of Workers × Time Taken
  • Inverse Proportion: If the amount of work is constant, the number of workers is inversely proportional to the time taken. More workers mean less time, and fewer workers mean more time.
  • Partial Work: If work is done in stages or by changing numbers of workers, calculate the work done in each stage and the remaining work.

Additional Information: Types of Work and Time Problems

Work and Time problems in quantitative aptitude can come in several forms:

  • Problems involving a fixed number of workers and the time taken.
  • Problems involving changes in the number of workers (men joining or leaving).
  • Problems involving workers with different efficiencies.
  • Problems involving alternating work days between workers.
  • Problems related to pipes and cisterns (which are analogous to work and time).

Solving these problems often involves calculating the total work unit (like man-days), the work done in different phases, and then using the remaining work to find the unknown variable (like time or number of workers).

Was this answer helpful?

Similar Questions

  1. A man undertakes to do a work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time?

  2. A work when done by 10 women is completed in 12 days. The same work can be completed in 8 days by 5 men. How many days will it take to complete when 6 women and 3 men are employed to perform the same job?


Important Questions from Work and Wages

  1. Which among the following are true about wages?

    A. The fair wage was something between minimum wage and living wage
    B. The Surplus Value Theory is associated with Maurice Dobb
    C. As per the Wages Fund Theory there exists pre-determined fund for the payment of wages
    D. Living wage provides workers and their families to live on some level considered adequate
    E. According to the "Bargaining Theory" there is an upper and lower limit on wage rates and the actual rates are determined by the capitalist

    Choose the most appropriate answer from the options given below:

  2. A shopkeeper employs a delivery boy and gives him a motorcycle for home delivery. For every delivery, the boy is given ₹ 5. At the end of the day, he also gets ₹ 2 for every kilometre of the distance covered in the day. The boy wants to earn more than ₹ 500 a day, but does not want to travel more than 100 km. Which of the following numbers of deliveries would definitely meet his target?
  3. 18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 15 hours a day?
  4. A building contractor employs 25 skilled workers and 5 unskilled workers. To a skilled worker he pays ₹30 per hour and to an unskilled worker ₹24 per hour. The average wage per hour (in ₹) paid by the contractor is:
  5. A and B can complete a piece of work in 15 days and 10 days respectively. They got a contract to complete the work for Rs. 35000. The share of A (in Rs.) in the contracted money will be:

Need Expert Advice?
Test Series
CDS img
Defence
UPSC CDS 2026 Mock Test Series
559 Tests 4 Tests Free
1821 Attempts
4.3(195)
English, Hindi
More Questions from CDS

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App