10 men working 8 hours a day can finish a work in 28 days. In how many days, 8 men working 5 hours a day with complete 50% of that work?
28
This problem is a classic example of a work and time problem where the total work done is directly proportional to the number of men, the hours they work per day, and the number of days they work. We can use a generalized formula to solve such problems efficiently.
The fundamental principle for work and time problems, especially when different groups of people work for different durations and complete varying amounts of work, is based on the idea that the "Man-Hours-Days" equivalent for a unit of work remains constant. The formula used is:
\[ \frac{M_1 \times D_1 \times H_1}{W_1} = \frac{M_2 \times D_2 \times H_2}{W_2} \]
Where:
Let's break down the information provided for both scenarios:
In the first situation, we have a group of men working to complete the entire work.
In the second situation, a different group of men working with different hours aims to complete 50% of that original work.
Now, let's substitute these values into our work-time formula:
\[ \frac{M_1 \times D_1 \times H_1}{W_1} = \frac{M_2 \times D_2 \times H_2}{W_2} \]
Substituting the values:
\[ \frac{10 \times 28 \times 8}{1} = \frac{8 \times D_2 \times 5}{0.5} \]
Let's simplify both sides of the equation:
Left side:
\[ 10 \times 28 \times 8 = 280 \times 8 = 2240 \]
So, the equation becomes:
\[ 2240 = \frac{8 \times D_2 \times 5}{0.5} \]
Right side:
First, calculate the product in the numerator:
\[ 8 \times D_2 \times 5 = 40 \times D_2 \]
Now, divide by 0.5 (which is the same as multiplying by 2):
\[ \frac{40 \times D_2}{0.5} = 40 \times D_2 \times 2 = 80 \times D_2 \]
So the full equation is:
\[ 2240 = 80 \times D_2 \]
To find \(D_2\), divide both sides by 80:
\[ D_2 = \frac{2240}{80} \]
\[ D_2 = 28 \]
Therefore, 8 men working 5 hours a day will complete 50% of that work in 28 days.
Based on the calculations using the men-days-hours-work formula, 8 men working 5 hours a day will take 28 days to complete 50% of the work.
A can complete a work alone in 8 days. B can complete the same work alone in 12 days. C alone complete the same work in 16 days. They complete the work in 3 days with the help of D. If they get Rs.12000 for the work, then how much money does the D get?
If 15 men can complete a work in 16 days by working 8 hours daily, then in how many days will 10 men complete the work by working 12 hours daily?
A can do a work in 12 days and B in 16 days. They undertook to do it for Rs. 6000 with the help of ‘C’ they completed the work in 6 days. What is the share of A?
Twenty lamps can be lighted for 6 hr a day for 20 days at a cost of Rs. 100. How much would be the cost of lighting 40 lamps, 8 hr for 12 days?
Six men can complete a job in two days. Four boys can complete the same job in eight days. In how many days would three men and six boys, working together, be able to complete the job?