A alone can do a work in 30 days, B alone in 40 days. They start together, but A leaves 5 days before the completion. Total work is completed in 18 days. In how many days did A work?
13 days
The whole work took 18 days, and A left 5 days before the work was completed.
So A worked for 18 – 5 = 13 days, and B worked for all 18 days.
Hence, 13 days.
A and B can complete a piece of work in 12 days and 18 days, respectively. A begins to do the work and they work alternately, one at a time, for one day each. The whole work will be completed in ________.
Neha is manufacturing plastic lunch boxes for a job. She got a project to manufacture some boxes, out of which she completed \(\frac{{15}}{{23}}\) of the project in 30 days. In how many days did she complete the entire project for the company?
8 men working 9 hours a day complete a piece of work in 20 days. In how many days can 7 men working for 10 hours a day complete the same piece of work?
A can do three-seventh of a work in 15 days and B can do two-fifth of the same work in 14 days. If A and B work together, then how long (in days) will they take to complete the work?
If 45 men can build a wall of 360 m length in 18 days, then how many men are required to build the same wall of 180 m length in 15 days?
By working 12 hours a day, 90 people can complete a work in 16 days. How much work will be left after 24 days if 70 people work for 8 hours per day?
15 men can complete a work in 15 days, whereas it takes 18 women to complete the work in 15 days. In how many days will 20 men and 9 women, together, complete the work? (Rounded off to complete number of days.)
13 men can complete a work in 7 days. After 3 days, 4 more men joined them. How many days will they now take to complete the remaining work?
Shivam can do a piece of work in 6 days and Vivek in 24 days. They started work together but Shivam left the work 3 days before its completion. In how many days was the work completed?
Ram reads 200 pages at the rate of 70 pages/hour in the morning. In the evening, when he was tired, he read 200 pages at the rate of 30 pages/hour. What was his average rate of reading, in pages per hour?
Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?
24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?
A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-
A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?