All Exams Test series for 1 year @ ₹349 only
Question

Seven machines take 7 minutes to make 7 identical toys. At the same rate, how many minutes would it take for 100 machines to make 100 toys?

The correct answer is
7

Understanding the Machine Rate

The problem states that 7 machines take 7 minutes to produce 7 identical toys. This implies a direct relationship between machines, toys, and time.

From the given information, we can deduce the rate of production:

  • If 7 machines make 7 toys in 7 minutes, then, on average, each machine makes 1 toy in those 7 minutes.
  • This means the time required for a single machine to make a single toy is 7 minutes.

Calculating Time for 100 Machines

We need to find the time it takes for 100 machines to make 100 toys, assuming they work at the same rate.

Since each machine takes 7 minutes to make one toy, and we have 100 machines working simultaneously:

  • Each of the 100 machines can work on one toy.
  • Each machine will complete its toy in 7 minutes.
  • Therefore, all 100 machines will finish their respective 100 toys in the same amount of time it takes one machine to finish one toy.

The calculation is as follows:

Rate of one machine = $\frac{1 \text{ toy}}{7 \text{ minutes}}$

Total rate of 100 machines = $100 \times \frac{1 \text{ toy}}{7 \text{ minutes}} = \frac{100}{7} \frac{\text{toys}}{\text{minute}}$

Time = $\frac{\text{Total Toys}}{\text{Total Rate}} = \frac{100 \text{ toys}}{\frac{100}{7} \frac{\text{toys}}{\text{minute}}} = 100 \times \frac{7}{100} \text{ minutes} = 7 \text{ minutes}$

Thus, it would take 7 minutes for 100 machines to make 100 toys.

Was this answer helpful?

Important Questions from Time and Work

  1. A works thrice as fast as B. If B can complete a work in 256 days independently, then find the number of days in which A and B can together
    finish the work.
  2. A can finish a job in 146 days, B can finish the same job in 219 days and C can finish the same job in 292 days. If all three are working together, how many days will they require to complete the same job?
  3. A finish a work in 1170 days and B can do the same work in 2340 days. Working together, they will complete the same work in how many days?
  4. A can finish a job in 102 days, B can finish the same job in 153 days and C can finish the same job in 204 days. If all three are working together, how many days will they require to complete the same job?
  5. M is thrice as efficient as workman as N and therefore is able to finish a job in 242 days less than N. Then N can finish the entire work in how many days?
Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App