All Exams Test series for 1 year @ ₹349 only
Question

Seven machines take 7 minutes to make 7 identical toys. At the same rate, how many minutes would it take for 100 machines to make 100 toys?

The correct answer is
7

Understanding the Machine Rate

The problem states that 7 machines take 7 minutes to produce 7 identical toys. This implies a direct relationship between machines, toys, and time.

From the given information, we can deduce the rate of production:

  • If 7 machines make 7 toys in 7 minutes, then, on average, each machine makes 1 toy in those 7 minutes.
  • This means the time required for a single machine to make a single toy is 7 minutes.

Calculating Time for 100 Machines

We need to find the time it takes for 100 machines to make 100 toys, assuming they work at the same rate.

Since each machine takes 7 minutes to make one toy, and we have 100 machines working simultaneously:

  • Each of the 100 machines can work on one toy.
  • Each machine will complete its toy in 7 minutes.
  • Therefore, all 100 machines will finish their respective 100 toys in the same amount of time it takes one machine to finish one toy.

The calculation is as follows:

Rate of one machine = $\frac{1 \text{ toy}}{7 \text{ minutes}}$

Total rate of 100 machines = $100 \times \frac{1 \text{ toy}}{7 \text{ minutes}} = \frac{100}{7} \frac{\text{toys}}{\text{minute}}$

Time = $\frac{\text{Total Toys}}{\text{Total Rate}} = \frac{100 \text{ toys}}{\frac{100}{7} \frac{\text{toys}}{\text{minute}}} = 100 \times \frac{7}{100} \text{ minutes} = 7 \text{ minutes}$

Thus, it would take 7 minutes for 100 machines to make 100 toys.

Was this answer helpful?

Important Questions from Time and Work

  1. Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?

  2. A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?

  3. Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?

  4. A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?

  5. lf 12 men can do a work in 20 days, in how many days will the work be done by 15 men-
Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App