P, Q and R alone can do a piece of work in 5, 6 and 4 days respectively. All three of them began the work together but Q left 1 days before completion of the work. In how many days was the work completed?
70/37 days
This problem involves calculating the total time taken to complete a piece of work when individuals work at different rates and one person leaves before the work is finished. We are given the time each person (P, Q, and R) takes to complete the work alone.
The work rate of a person is the amount of work they can do in one day. It is the reciprocal of the time they take to complete the whole work alone.
The problem states that all three (P, Q, and R) started the work together. However, Q left 1 day before the completion of the work. This means:
Let's assume the total number of days the work was completed in is \(T\) days.
The total work done is the sum of the work done by P, Q, and R over the days they worked. The total work is considered as 1 unit.
Work done by P in \(T\) days = (P's rate) \(\times\) (Number of days P worked) = \(\frac{1}{5} \times T = \frac{T}{5}\)
Work done by Q in \(T-1\) days = (Q's rate) \(\times\) (Number of days Q worked) = \(\frac{1}{6} \times (T-1) = \frac{T-1}{6}\)
Work done by R in \(T\) days = (R's rate) \(\times\) (Number of days R worked) = \(\frac{1}{4} \times T = \frac{T}{4}\)
The total work done is the sum of these amounts, which equals 1 (the total work).
So, the equation is:
$$\frac{T}{5} + \frac{T-1}{6} + \frac{T}{4} = 1$$
To solve for \(T\), we need to find a common denominator for the fractions. The least common multiple (LCM) of 5, 6, and 4 is 60.
Multiply the entire equation by 60 to eliminate the denominators:
$$60 \times \left(\frac{T}{5}\right) + 60 \times \left(\frac{T-1}{6}\right) + 60 \times \left(\frac{T}{4}\right) = 60 \times 1$$
Simplify each term:
$$12T + 10(T-1) + 15T = 60$$
Distribute the 10 in the second term:
$$12T + 10T - 10 + 15T = 60$$
Combine the terms with \(T\):
$$(12T + 10T + 15T) - 10 = 60$$
$$37T - 10 = 60$$
Add 10 to both sides of the equation:
$$37T = 60 + 10$$
$$37T = 70$$
Divide by 37 to find \(T\):
$$T = \frac{70}{37}$$
So, the work was completed in \(\frac{70}{37}\) days.
The total number of days required to complete the work is \(\frac{70}{37}\) days. This fits one of the given options.
| Concept | Explanation | Formula/Relation |
|---|---|---|
| Work Rate | The amount of work done by a person or team per unit of time. | Work Rate = \(\frac{1}{\text{Time taken to complete the work}}\) |
| Time Taken | The total time required to complete a specific amount of work. | Time Taken = \(\frac{\text{Total Work}}{\text{Total Work Rate}}\) |
| Total Work | Usually considered as 1 unit when individual rates are given as fractions of total work per unit time. | Work = Rate \(\times\) Time |
| Combined Rate | The sum of individual rates when multiple people work together. | Rate\(_\text{A+B}\) = Rate\(_\text{A}\) + Rate\(_\text{B}\) |
Time and work problems often involve calculating the efficiency of individuals or groups and how long it takes them to complete a task, sometimes under varying conditions (like people joining or leaving). Key to solving these is understanding the inverse relationship between time and work rate: the faster someone works, the less time they take.
Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?
A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?
Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?
A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?