P, Q and R alone can do a piece of work in 5, 6 and 4 days respectively. All three of them began the work together but Q left 1 days before completion of the work. In how many days was the work completed?
70/37 days
This problem involves calculating the total time taken to complete a piece of work when individuals work at different rates and one person leaves before the work is finished. We are given the time each person (P, Q, and R) takes to complete the work alone.
The work rate of a person is the amount of work they can do in one day. It is the reciprocal of the time they take to complete the whole work alone.
The problem states that all three (P, Q, and R) started the work together. However, Q left 1 day before the completion of the work. This means:
Let's assume the total number of days the work was completed in is \(T\) days.
The total work done is the sum of the work done by P, Q, and R over the days they worked. The total work is considered as 1 unit.
Work done by P in \(T\) days = (P's rate) \(\times\) (Number of days P worked) = \(\frac{1}{5} \times T = \frac{T}{5}\)
Work done by Q in \(T-1\) days = (Q's rate) \(\times\) (Number of days Q worked) = \(\frac{1}{6} \times (T-1) = \frac{T-1}{6}\)
Work done by R in \(T\) days = (R's rate) \(\times\) (Number of days R worked) = \(\frac{1}{4} \times T = \frac{T}{4}\)
The total work done is the sum of these amounts, which equals 1 (the total work).
So, the equation is:
$$\frac{T}{5} + \frac{T-1}{6} + \frac{T}{4} = 1$$
To solve for \(T\), we need to find a common denominator for the fractions. The least common multiple (LCM) of 5, 6, and 4 is 60.
Multiply the entire equation by 60 to eliminate the denominators:
$$60 \times \left(\frac{T}{5}\right) + 60 \times \left(\frac{T-1}{6}\right) + 60 \times \left(\frac{T}{4}\right) = 60 \times 1$$
Simplify each term:
$$12T + 10(T-1) + 15T = 60$$
Distribute the 10 in the second term:
$$12T + 10T - 10 + 15T = 60$$
Combine the terms with \(T\):
$$(12T + 10T + 15T) - 10 = 60$$
$$37T - 10 = 60$$
Add 10 to both sides of the equation:
$$37T = 60 + 10$$
$$37T = 70$$
Divide by 37 to find \(T\):
$$T = \frac{70}{37}$$
So, the work was completed in \(\frac{70}{37}\) days.
The total number of days required to complete the work is \(\frac{70}{37}\) days. This fits one of the given options.
| Concept | Explanation | Formula/Relation |
|---|---|---|
| Work Rate | The amount of work done by a person or team per unit of time. | Work Rate = \(\frac{1}{\text{Time taken to complete the work}}\) |
| Time Taken | The total time required to complete a specific amount of work. | Time Taken = \(\frac{\text{Total Work}}{\text{Total Work Rate}}\) |
| Total Work | Usually considered as 1 unit when individual rates are given as fractions of total work per unit time. | Work = Rate \(\times\) Time |
| Combined Rate | The sum of individual rates when multiple people work together. | Rate\(_\text{A+B}\) = Rate\(_\text{A}\) + Rate\(_\text{B}\) |
Time and work problems often involve calculating the efficiency of individuals or groups and how long it takes them to complete a task, sometimes under varying conditions (like people joining or leaving). Key to solving these is understanding the inverse relationship between time and work rate: the faster someone works, the less time they take.
Surbhi can do a piece of work in 24 days. She completed 3/8 of the work and then left it. Amit can complete the remaining work in 10 days. Working together, they will complete 125% of the same work in:
Rama and Hari can together finish a piece of work in 15 day. Rama works twice as fast as Hari, then Hari alone can finish work in :
Anil, Deepak and Dinesh together can complete a work in 35 days. Anil and Dinesh together can complete the same work in 60 days. In how many days Deepak alone can complete the same work?
Anu is four times as good as Binni in completing a task. Together they finish the same task in 7 hours. In how many hours will Anu alone complete the task?
P, Q and R can complete a work in 10 days, 20 days and 30 days, respectively, working alone. How soon can the work be completed if P is assisted by Q and R on alternate days?