Question

Match the brick masonry bond type in Group I with the corresponding illustration in Group II

 

Group IGroup II
(P) Rat Trap(1)
(Q) English(2)
(R) Flemish(3)
(S) Stretcher(4)
 (5)

The correct answer is
P-4, Q-1, R-2, S-5

To match the brick masonry bond types from Group I with the corresponding illustrations in Group II, let's first understand each bond type:

  1. Rat Trap Bond: This bond uses a cavity to reduce material usage and provides better thermal insulation. The image shows bricks laid creating pockets, typical of a rat trap bond.
  2. English Bond: This consists of alternating courses of headers and stretchers, providing strong load-bearing capacity. The illustration displays the alternate rows clearly.
  3. Flemish Bond: This pattern involves the placement of headers and stretchers alternately in each course. The distinctive alternating pattern is visible in the image.
  4. Stretcher Bond: Used for walls of half-brick thickness, this pattern consists entirely of stretchers. The continuous stretchers can be identified in the visual representation.

Matching them with Group II:

Group IGroup II
(P) Rat Trap(4) 
(Q) English(1) 
(R) Flemish(2) 
(S) Stretcher(5) 

Thus, the correct answer is:

P-4, Q-1, R-2, S-5

Was this answer helpful?

Important Questions from Building Construction Techniques

  1. Cold joint' refers to the
  2. Match the Elements in Group - I with their Applications in Group - II
    Group - IGroup - II
    P Bracket1 Door
    Q Baluster2 Dome
    R Key stone3 Cornice
    S Holdfast4 Arch
    5 Staircase
  3. Match the Vibrator Types in Group-I with their related Areas of Application in Group-II
    Group-IGroup-II
    P Needle Vibrator1 Concrete Pavement
    Q Shutter Vibrator2 Pre-cast Concrete Unit
    R Surface Vibrator3 Beam-Column Junction
    S Table Vibrator4 Retaining Wall
    5 Slip Forming
  4. Match the type of Temporary Structures in Group - I with their corresponding Functions in Group - II
    Group-IGroup-II
    P Scaffolding1 To support unsafe structure
    Q Formwork2 To support platforms for workmen and materials at raised height during construction
    R Shoring3 Removal of water from pits
    S Underpinning4 Mould for RCC Structure
    5 Strengthening the existing foundation
  5. Associate the terms in Group-I with the building hardware in Group-II

           Group-IGroup-II
    P Parliamentary1Bar
    Q Aldrop2Lock
    R Panic3Hinge
    S Mortise4Bolt