Match the type of Temporary Structures in Group - I with their corresponding Functions in Group - II
Group-IGroup-II
P Scaffolding1 To support unsafe structure
Q Formwork2 To support platforms for workmen and materials at raised height during construction
R Shoring3 Removal of water from pits
S Underpinning4 Mould for RCC Structure
5 Strengthening the existing foundation

The correct answer is
P-2, Q-4, R-1, S-5

Matching Temporary Structures with Functions

This solution involves matching the temporary construction structures listed in Group I with their appropriate functions from Group II.

Group I: Temporary Structures

  • P: Scaffolding - Used to support platforms for workers and materials.
  • Q: Formwork - Acts as a mould for concrete structures.
  • R: Shoring - Provides temporary support to unstable or unsafe structures.
  • S: Underpinning - Strengthens or supports an existing foundation.

Group II: Functions

  • 1: To support unsafe structure
  • 2: To support platforms for workmen and materials at raised height during construction
  • 3: Removal of water from pits
  • 4: Mould for RCC Structure
  • 5: Strengthening the existing foundation

Structure-Function Matching

The correct matching is determined as follows:

  • Scaffolding (P) supports platforms at height, matching function 2.
  • Formwork (Q) serves as a mould for concrete, matching function 4.
  • Shoring (R) supports unsafe structures, matching function 1.
  • Underpinning (S) strengthens foundations, matching function 5.

Final Matched Option

Combining these matches gives the result: P-2, Q-4, R-1, S-5. This corresponds to the first option.

Was this answer helpful?

Important Questions from Building Construction Techniques

  1. Match the Elements in Group - I with their Applications in Group - II
    Group - IGroup - II
    P Bracket1 Door
    Q Baluster2 Dome
    R Key stone3 Cornice
    S Holdfast4 Arch
    5 Staircase
  2. Match the Vibrator Types in Group-I with their related Areas of Application in Group-II
    Group-IGroup-II
    P Needle Vibrator1 Concrete Pavement
    Q Shutter Vibrator2 Pre-cast Concrete Unit
    R Surface Vibrator3 Beam-Column Junction
    S Table Vibrator4 Retaining Wall
    5 Slip Forming
  3. The number of standard cement bags required to prepare 1400 kg of concrete in the ratio of 1:2:4 (mixed by weight batching) is _______________

  4. An element constructed at intervals along the length of a wall to stabilize it against overturning is
  5. Cold joint' refers to the
Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App