Question

Match the Vibrator Types in Group-I with their related Areas of Application in Group-II
Group-IGroup-II
P Needle Vibrator1 Concrete Pavement
Q Shutter Vibrator2 Pre-cast Concrete Unit
R Surface Vibrator3 Beam-Column Junction
S Table Vibrator4 Retaining Wall
5 Slip Forming

The correct answer is
P-3, Q-4, R-1, S-2

Vibrator Type Applications Explained

This solution clarifies the matching between vibrator types (Group I) and their construction applications (Group II).

Needle Vibrator (P) Applications

Matches with: 3. Beam-Column Junction

Ideal for internal compaction in narrow, heavily reinforced areas like beam-column junctions.

Shutter Vibrator (Q) Applications

Matches with: 4. Retaining Wall

Used externally on formwork (shutters), effective for consolidating concrete in walls, including retaining walls.

Surface Vibrator (R) Applications

Matches with: 1. Concrete Pavement

Designed for external vibration on the concrete surface, suitable for slabs and pavements.

Table Vibrator (S) Applications

Matches with: 2. Pre-cast Concrete Unit

Utilized for pre-cast elements; vibrates moulds placed on a table for uniform compaction.

Final Matches: Group I to Group II

The correct pairings derived are:

  • P - 3
  • Q - 4
  • R - 1
  • S - 2
Was this answer helpful?

Important Questions from Building Construction Techniques

  1. Match the Elements in Group - I with their Applications in Group - II
    Group - IGroup - II
    P Bracket1 Door
    Q Baluster2 Dome
    R Key stone3 Cornice
    S Holdfast4 Arch
    5 Staircase
  2. Match the type of Temporary Structures in Group - I with their corresponding Functions in Group - II
    Group-IGroup-II
    P Scaffolding1 To support unsafe structure
    Q Formwork2 To support platforms for workmen and materials at raised height during construction
    R Shoring3 Removal of water from pits
    S Underpinning4 Mould for RCC Structure
    5 Strengthening the existing foundation
  3. The number of standard cement bags required to prepare 1400 kg of concrete in the ratio of 1:2:4 (mixed by weight batching) is _______________

  4. An element constructed at intervals along the length of a wall to stabilize it against overturning is
  5. Cold joint' refers to the
Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App