The number of standard cement bags required to prepare 1400 kg of concrete in the ratio of 1:2:4 (mixed by weight batching) is _______________
This solution explains how to calculate the number of standard cement bags required for a specific quantity of concrete using weight batching.
Determine the total parts in the given ratio: The ratio for concrete is 1:2:4 (Cement:Sand:Aggregate). Total parts = $1 + 2 + 4 = 7$.
Calculate the weight of cement needed. The total concrete weight is 1400 kg. Weight of Cement = $ \left( \frac{\text{Cement Part}}{\text{Total Parts}} \right) \times \text{Total Weight} $ Weight of Cement = $ \left( \frac{1}{7} \right) \times 1400 \, \text{kg} = 200 \, \text{kg} $.
Find the number of standard cement bags. A standard cement bag weighs 50 kg. Number of Bags = $ \frac{\text{Total Weight of Cement}}{\text{Weight per Bag}} $ Number of Bags = $ \frac{200 \, \text{kg}}{50 \, \text{kg/bag}} = 4 \, \text{bags} $.
Therefore, 4 standard cement bags are required.
| Group - I | Group - II |
| P Bracket | 1 Door |
| Q Baluster | 2 Dome |
| R Key stone | 3 Cornice |
| S Holdfast | 4 Arch |
| 5 Staircase |
| Group-I | Group-II |
| P Needle Vibrator | 1 Concrete Pavement |
| Q Shutter Vibrator | 2 Pre-cast Concrete Unit |
| R Surface Vibrator | 3 Beam-Column Junction |
| S Table Vibrator | 4 Retaining Wall |
| 5 Slip Forming |
| Group-I | Group-II |
| P Scaffolding | 1 To support unsafe structure |
| Q Formwork | 2 To support platforms for workmen and materials at raised height during construction |
| R Shoring | 3 Removal of water from pits |
| S Underpinning | 4 Mould for RCC Structure |
| 5 Strengthening the existing foundation |