Levelling in which staff and readings and the distance between the points is required is called:
profile levelling
Levelling is a surveying procedure used to determine the relative heights of points on the earth's surface. Different methods of levelling are employed depending on the purpose of the survey and the required accuracy. The question asks about a specific type of levelling that requires the use of a levelling staff, taking readings on this staff, and measuring the distance between the points being levelled.
Let's examine each option to see which one best matches the description provided in the question:
Based on the characteristics of each levelling method, the process that specifically requires staff, staff readings (including intermediate sights), and the distance between points to determine the elevation along a defined line is profile levelling.
In profile levelling, the distances are measured along the line (often using a tape or electronic distance measurement) to locate the points where staff readings are taken. These distances are crucial for plotting the profile, which is a graph showing the elevation variation along the line.
| Levelling Method | Requires Staff? | Requires Staff Readings? | Requires Distance Between Points for Detailed Profile? |
|---|---|---|---|
| Profile Levelling | Yes | Yes (BS, IS, FS) | Yes |
| Fly Levelling | Yes | Yes (BS, FS) | Generally No (not detailed intermediate distances) |
| Trigonometric Levelling | No (uses vertical angles & distances) | No | Yes (horizontal/slope distance) |
| Auto Levelling | Yes (instrument type, used in methods) | Yes (instrument type) | Depends on the method used with it |
Therefore, the levelling method described, which requires staff, staff readings, and the distance between points, is profile levelling.
| Term | Definition | Relevance to Question |
|---|---|---|
| Levelling Staff | A graduated rod used to measure vertical distances from the line of sight of a levelling instrument. | Required in methods like profile and fly levelling. |
| Backsight (BS) | The first staff reading taken after setting up the level, usually on a point of known or assumed elevation. | Part of staff readings required in profile and fly levelling. |
| Foresight (FS) | The last staff reading taken before moving the level, usually on a point whose elevation is to be determined or a turning point. | Part of staff readings required in profile and fly levelling. |
| Intermediate Sight (IS) | A staff reading taken on any point whose elevation is required, other than a backsight or foresight. | Crucial for determining elevations at various points along the line in profile levelling. |
| Reduced Level (RL) | The elevation of a point with respect to a datum (reference surface). | The ultimate goal of levelling methods is to determine RLs. |
| Height of Instrument (HI) | The elevation of the line of sight of the level instrument. Calculated as RL of BS point + BS reading. | Used in the 'Height of Instrument' method of calculating levels. |
Profile levelling is a fundamental technique in civil engineering and surveying for planning and designing linear infrastructure projects. Its applications include:
The detailed information about elevations and distances collected during profile levelling allows engineers to create a vertical cross-section of the ground along the proposed route, which is essential for subsequent design stages.
Calculate the true reduced level (m) of a point A after correcting the refraction and curvature. The staff reading at the point taken from an instrument set at a distance of 2 km from the point A is 2.56 m. The staff reading from the same station on a bench mark of reduced level is 100 m is 1.34 m.
The dumpy level is most suitable for levelling survey:
Which level has internal compensator mechanism to automatically adjust the line of sight?
Bench mark is established by -
Which of the following is a correct statement with reference to determining reduced level of a point using rise and fall method?