If P can finish a job in 3 hours and Q can finish the same job in 6 hours independently, then they together will finish the job in x minutes. Find the value of x .
120
The question asks us to find the time it takes for two individuals, P and Q, to complete a specific job when they work together. We are given the time each person takes to finish the job independently. The final answer needs to be in minutes.
Here's what we know:
Our goal is to calculate the value of x.
To solve problems involving work and time, it's helpful to calculate the work rate of each person. The work rate is the amount of work done per unit of time.
If a person takes $T$ hours to complete a job, their work rate is $\frac{1}{T}$ of the job per hour.
When P and Q work together on the same job, their individual work rates combine. The combined work rate is the sum of their individual rates.
Combined work rate = P's work rate + Q's work rate
Combined work rate = $\frac{1}{3} + \frac{1}{6}$ job per hour.
To add these fractions, we find a common denominator, which is 6.
So, Combined work rate = $\frac{2}{6} + \frac{1}{6} = \frac{2+1}{6} = \frac{3}{6}$
Simplifying the fraction $\frac{3}{6}$, we get $\frac{1}{2}$.
Combined work rate = $\frac{1}{2}$ job per hour.
This means that when working together, P and Q complete half of the job in one hour.
The time taken to complete the entire job when working together is the reciprocal of the combined work rate.
Time taken together in hours = $\frac{1}{\text{Combined work rate}}$
Time taken together in hours = $\frac{1}{1/2} = 1 \times 2 = 2$ hours.
The question asks for the time in minutes (x minutes). We have calculated the time in hours, which is 2 hours.
To convert hours to minutes, we multiply by 60, since 1 hour = 60 minutes.
Time taken together in minutes = Time in hours $\times$ 60
Time taken together in minutes = $2 \times 60 = 120$ minutes.
Therefore, the value of x is 120.
Let's summarize the steps to find the time taken when P and Q work together:
| Step | Concept | Calculation |
|---|---|---|
| 1 | P's Work Rate (Job/Hour) | $\frac{1}{3}$ |
| 2 | Q's Work Rate (Job/Hour) | $\frac{1}{6}$ |
| 3 | Combined Work Rate (Job/Hour) | $\frac{1}{3} + \frac{1}{6} = \frac{2}{6} + \frac{1}{6} = \frac{3}{6} = \frac{1}{2}$ |
| 4 | Time Taken Together (Hours) | $\frac{1}{\text{Combined Rate}} = \frac{1}{1/2} = 2$ hours |
| 5 | Time Taken Together (Minutes) | Time in Hours $\times$ 60 = $2 \times 60 = 120$ minutes |
The job will be finished in 120 minutes when P and Q work together. So, x = 120.
Understanding the core concepts of work and time is crucial for solving these types of problems.
| Concept | Explanation | Relation to other concepts |
|---|---|---|
| Work Rate | The fraction or amount of a job completed per unit of time. | Rate = $\frac{1}{\text{Time}}$ |
| Time Taken | The total time required to complete a specific amount of work (usually 1 full job). | Time = $\frac{1}{\text{Rate}}$ |
| Total Work | Usually represented as 1 unit for completing one job. | Total Work = Rate $\times$ Time |
| Combined Rate | The sum of individual rates when multiple people work together. | $R_{\text{combined}} = R_1 + R_2 + ...$ |
| Time Together | The time taken to complete the job when working together. | $T_{\text{together}} = \frac{1}{R_{\text{combined}}}$ |
Work and time problems often appear in various exams. Here are some tips:
Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?
A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?
Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?
A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?