We need to find out how many hours it will take for 7 persons to paint 7 walls of equal area, given that 5 persons can paint 5 walls in 5 hours.
Let's break down the given scenario:
\(\text{Rate of work per person} = \frac{\text{Total number of walls}}{\text{Number of persons} \times \text{Number of hours}} = \frac{5 \text{ walls}}{5 \text{ persons} \times 5 \text{ hours}} = \frac{1}{5} \text{ (walls per person per hour) }\)
\(\text{Total rate for 7 persons} = 7 \times \frac{1}{5} = \frac{7}{5} \text{ walls per hour}\)
\(\text{Time} = \frac{\text{Total number of walls}}{\text{Total rate}} = \frac{7}{\frac{7}{5}} = 5 \text{ hours}\)
Thus, the required time for 7 persons to paint 7 walls is 5 hours.
The correct option is 5.
Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?
A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?
Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?
A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?