All Exams Test series for 1 year @ ₹349 only
Question

If five persons take five hours to paint five walls of equal area, how many hours will 7 persons take to paint 7 walls of equal area, provided both the sets of walls are identical ?

The correct answer is
5

We need to find out how many hours it will take for 7 persons to paint 7 walls of equal area, given that 5 persons can paint 5 walls in 5 hours.

Let's break down the given scenario:

  1. Initial Rate of Work: Here, we are told that 5 persons take 5 hours to paint 5 walls. This means that the \(5\) persons are working together and they complete \(5\) walls in \(5\) hours.
  2. From this, we can deduce that:

\(\text{Rate of work per person} = \frac{\text{Total number of walls}}{\text{Number of persons} \times \text{Number of hours}} = \frac{5 \text{ walls}}{5 \text{ persons} \times 5 \text{ hours}} = \frac{1}{5} \text{ (walls per person per hour) }\)

  1. New Scenario: Now, we want to calculate how long it takes for 7 persons to paint 7 walls.
  2. Since each person paints \(\frac{1}{5}\) wall per hour, 7 persons will paint walls at the rate of:

\(\text{Total rate for 7 persons} = 7 \times \frac{1}{5} = \frac{7}{5} \text{ walls per hour}\)

  1. The total number of walls to be painted is 7. Therefore, the time required for 7 persons to paint 7 walls is given by:

\(\text{Time} = \frac{\text{Total number of walls}}{\text{Total rate}} = \frac{7}{\frac{7}{5}} = 5 \text{ hours}\)

Thus, the required time for 7 persons to paint 7 walls is 5 hours.

The correct option is 5.

Was this answer helpful?

Important Questions from Time and Work

  1. Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?

  2. A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?

  3. Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?

  4. A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?

  5. lf 12 men can do a work in 20 days, in how many days will the work be done by 15 men-
Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App