We need to find out how many hours it will take for 7 persons to paint 7 walls of equal area, given that 5 persons can paint 5 walls in 5 hours.
Let's break down the given scenario:
\(\text{Rate of work per person} = \frac{\text{Total number of walls}}{\text{Number of persons} \times \text{Number of hours}} = \frac{5 \text{ walls}}{5 \text{ persons} \times 5 \text{ hours}} = \frac{1}{5} \text{ (walls per person per hour) }\)
\(\text{Total rate for 7 persons} = 7 \times \frac{1}{5} = \frac{7}{5} \text{ walls per hour}\)
\(\text{Time} = \frac{\text{Total number of walls}}{\text{Total rate}} = \frac{7}{\frac{7}{5}} = 5 \text{ hours}\)
Thus, the required time for 7 persons to paint 7 walls is 5 hours.
The correct option is 5.
Surbhi can do a piece of work in 24 days. She completed 3/8 of the work and then left it. Amit can complete the remaining work in 10 days. Working together, they will complete 125% of the same work in:
Rama and Hari can together finish a piece of work in 15 day. Rama works twice as fast as Hari, then Hari alone can finish work in :
Anil, Deepak and Dinesh together can complete a work in 35 days. Anil and Dinesh together can complete the same work in 60 days. In how many days Deepak alone can complete the same work?
Anu is four times as good as Binni in completing a task. Together they finish the same task in 7 hours. In how many hours will Anu alone complete the task?
P, Q and R can complete a work in 10 days, 20 days and 30 days, respectively, working alone. How soon can the work be completed if P is assisted by Q and R on alternate days?