Question

Choose the correct sequence for erecting an overhead transmission line.

 1. Foundation work 

2. Tower erection 

3. Conductor stringing 

4. Insulator installation

This question was previously asked in
RRB ALP 2025 CBT 2 Wiremen Question Paper (28-Jul-2026) (Shift 2)
The correct answer is

Foundation work, Tower erection, Insulator installation, Conductor stringing

To determine the correct sequence for erecting an overhead transmission line, it's essential to understand the typical process involved in the construction. Here's a step-by-step explanation:

  1. Foundation work: The first step in the construction of an overhead transmission line is preparing the foundation for the towers. This involves site preparation, excavation, and the setting of foundations to support the tower structures.
  2. Tower erection: Once the foundation is ready, the next step is erecting the towers. Tower segments are assembled and raised into place on the prepared foundations.
  3. Insulator installation: After the towers have been erected, insulators are affixed to the towers. Insulators are essential for supporting conductors and preventing unwanted flow of current to the tower structures.
  4. Conductor stringing: Finally, the conductors are strung between the towers. This involves pulling the conductor wire through pulleys fixed at the insulator points along the towers, and then tensioning them correctly.

With the above explanation, the correct sequence for erecting an overhead transmission line is: Foundation work, Tower erection, Insulator installation, Conductor stringing. This aligns with the provided correct answer.

This logical sequence ensures stability, safety, and efficiency in the construction of transmission lines.

Was this answer helpful?

Similar Questions

  1. Steel poles are painted to prevent them from:

  2. What is the purpose of a lighting arrester connected between the line and earth in a power S/M?

  3. Domestic customers are provided with single phase supply voltage of

  4. From the given options, identify the type of lug used for connecting an aluminum cable to a copper bus bar.

  5. In which of the following regions of a cable, voltage stress is maximum?

  6. What is the color of neutral in three core flexible cables?

  7. The current carrying capacity of cables is:

  8. The SMPS is used to transform power from AC or DC to:

  9. The current on a high voltage line is measured using:

  10. Which among the below is not generally used for distribution systems?


Important Questions from Transmission and Distribution

  1. The capacitance and inductance per unit length of a three-phase line, operating at 110 kV are 0.01 μF and 2.5 mH. The surge impedance of the line is:

  2. Which of the following statements about the EHV lines is INCORRECT?

  3. Steel poles are painted to prevent them from:

  4. What is the purpose of a lighting arrester connected between the line and earth in a power S/M?

  5. Domestic customers are provided with single phase supply voltage of

Need Expert Advice?
Upcoming Exams
RRB JE
October 27, 2026
RRB ALP
November 03, 2026
Test Series
RRB ALP img
Railways
RRB ALP 2026 Mock Test series
1035 Tests 1 Tests Free
1298 Attempts
4.3(246)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App