Choose the correct sequence for erecting an overhead transmission line.

 1. Foundation work 

2. Tower erection 

3. Conductor stringing 

4. Insulator installation

This question was previously asked in
RRB NTPC 2025 Graduate Level CBT 1 Question Paper (25-Mar-2026) (Shift 3)
The correct answer is

Foundation work, Tower erection, Insulator installation, Conductor stringing

To determine the correct sequence for erecting an overhead transmission line, it's essential to understand the typical process involved in the construction. Here's a step-by-step explanation:

  1. Foundation work: The first step in the construction of an overhead transmission line is preparing the foundation for the towers. This involves site preparation, excavation, and the setting of foundations to support the tower structures.
  2. Tower erection: Once the foundation is ready, the next step is erecting the towers. Tower segments are assembled and raised into place on the prepared foundations.
  3. Insulator installation: After the towers have been erected, insulators are affixed to the towers. Insulators are essential for supporting conductors and preventing unwanted flow of current to the tower structures.
  4. Conductor stringing: Finally, the conductors are strung between the towers. This involves pulling the conductor wire through pulleys fixed at the insulator points along the towers, and then tensioning them correctly.

With the above explanation, the correct sequence for erecting an overhead transmission line is: Foundation work, Tower erection, Insulator installation, Conductor stringing. This aligns with the provided correct answer.

This logical sequence ensures stability, safety, and efficiency in the construction of transmission lines.

Was this answer helpful?

Similar Questions

  1. In which situation is DC transmission preferred over AC transmission in power networks?

  2. What is the purpose of the Cable Sheath Continuity Test in underground cables?

  3. Which of the following methods is used to detect an oil leak in an underground oil filled cable joint without excavation?

  4. While repairing overhead transmission lines, which type of wire joint is most suitable for joining two stranded conductors with high current carrying requirements?

  5. Which of the following equipment provides surge protection in substations?

  6. Which type of substation would be strategically installed on a high-voltage transmission line to improve network reliability by isolating faults without changing voltage levels?

  7. Which of the following steps helps prevent void formation during epoxy resin casting in underground cable joints?

  8. What is the purpose of a pre-molded joint in underground cables?

  9. A technician is using the Murray loop test to locate a ground fault in a two-core cable. Which essential component must be connected to complete the test setup?


Important Questions from Transmission and Distribution

  1. For household wiring and small units, the following should be used as a safety measure:

  2. The minimum clearance distance that equipment should be kept away from 50 kV power lines is:

  3. What is the purpose of a lighting arrester connected between the line and earth in a power S/M?

  4. From the given options, identify the type of lug used for connecting an aluminum cable to a copper bus bar.

  5. What is the color of neutral in three core flexible cables?

Need Expert Advice?
Upcoming Exams
RRB NTPC
September 27, 2026
Test Series
RRB ALP img
Railways
RRB ALP 2026 Mock Test series
1035 Tests 1 Tests Free
741 Attempts
4.3(233)
English, Hindi
More Questions from RRB ALP

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App