Question

Assume that the software team defines a project risk with 80% probability of occurrence of risk in the following manner :

Only 70 percent of the software components scheduled for reuse will be integrated into the application and the remaining functionality will have to be custom developed. If 60 reusable components were planned with average component size as 100 LOC and software engineering cost for each LOC as \(\$\) 14, then the risk exposure would be

This question was previously asked in
UGC NET 2014 Paper 1 Question Paper (28-Dec-2014)
The correct answer is

\(\$\) 20,160

Risk exposure is the expected loss from a risk: \(RE = P \times C\), where P is the probability that the risk occurs and C is the cost incurred if it does.

If only 70% of the 60 planned components are reused, the remaining 30% must be built from scratch: \(0.30 \times 60 = 18\) components.

Size to be custom developed = \(18 \times 100 = 1800\) LOC, so the cost of the risk is \(C = 1800 \times \$14 = \$25{,}200\).

With P = 0.80, \(RE = 0.80 \times \$25{,}200 = \$20{,}160\).

Hence, the answer is \(\$\) 20,160.

Was this answer helpful?

Similar Questions

  1. Identify the correct statements from the following regarding spiral model.

    A. Spiral model is an incremental process model.

    B. Spiral model is a risk - driven process mode.

    C. Spiral model is an acyclic balancing approach.

    D. Spiral model involves a set of anchor point milestone.

    Choose the correct answer from the options given below:


Important Questions from Spiral - Teaching

  1. Which statement(s) is/are false?

    P: The Cleanroom software-engineering methodology for high reliability uses incremental software development.

    Q: Clean-room reimplementation, with implementers separated from the original source code, is a technique for reducing unconscious copying of that code.

    Choose the correct answer from the code given below.

  2. Spiral model of software development is also known as ______.

  3. Identify the correct statements from the following regarding spiral model.

    A. Spiral model is an incremental process model.

    B. Spiral model is a risk - driven process mode.

    C. Spiral model is an acyclic balancing approach.

    D. Spiral model involves a set of anchor point milestone.

    Choose the correct answer from the options given below:

  4. ___________ model couples the iterative nature of the prototyping with the controlled and systematic aspects of the linear sequential model.

Need Expert Advice?
Upcoming Exams
CTET
December 12, 2026
Test Series
UGC NET img
Teaching
UGC NET (Paper 2) 2026 Mock Test Series
796 Tests 2 Tests Free
4.4(39)
English
More Questions from UGC NET

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App