All Exams Test series for 1 year @ ₹349 only
Question

Anil alone takes 2 hrs 40 min to complete a work and sumit alone can complete the same work in half time of Anil How much time will be taken by sumit to complete the work?

The correct answer is

80 mins

Calculating Work Time for Anil and Sumit

This problem involves calculating the time taken by two individuals, Anil and Sumit, to complete a specific work. We are given the time Anil takes and the relationship between Anil's time and Sumit's time.

Understanding the Given Information

  • Anil alone takes 2 hours and 40 minutes to complete the work.
  • Sumit alone can complete the same work in half the time taken by Anil.

We need to find the time Sumit takes to complete the work in minutes.

Convert Anil's Work Time to Minutes

First, let's convert Anil's total work time from hours and minutes into minutes.

We know that 1 hour = 60 minutes.

Anil's time = 2 hours + 40 minutes

Anil's time in minutes = $(2 \times 60)$ minutes + 40 minutes

Anil's time in minutes = $120$ minutes + 40 minutes

Anil's time in minutes = $160$ minutes

Determine Sumit's Work Time

The problem states that Sumit takes half the time Anil takes to complete the work.

Sumit's time = $\frac{1}{2} \times$ Anil's time

Sumit's time = $\frac{1}{2} \times 160$ minutes

Sumit's time = $\frac{160}{2}$ minutes

Sumit's time = $80$ minutes

Therefore, Sumit will take 80 minutes to complete the work alone.

Revision Table: Work and Time Concepts

Concept Description Relationship
Work The total task to be completed. Often considered as 1 unit of work. Work = Rate $\times$ Time
Time The duration taken to complete the work. Time = $\frac{\text{Work}}{\text{Rate}}$
Rate (Efficiency) The amount of work done per unit of time. Rate = $\frac{\text{Work}}{\text{Time}}$

Additional Information: Understanding Work Rate

In work and time problems, the concept of work rate is very useful. The rate of work is inversely proportional to the time taken to complete the work. This means if someone takes less time, they have a higher work rate (are more efficient), and if they take more time, they have a lower work rate.

Let's consider the work rate for Anil and Sumit:

Assume the total work is 1 unit.

  • Anil's time = 160 minutes.
  • Anil's work rate = $\frac{\text{Work}}{\text{Time}} = \frac{1}{160}$ work per minute.
  • Sumit's time = 80 minutes.
  • Sumit's work rate = $\frac{\text{Work}}{\text{Time}} = \frac{1}{80}$ work per minute.

Notice that Sumit's rate ($\frac{1}{80}$) is double Anil's rate ($\frac{1}{160}$), which makes sense because Sumit takes half the time to complete the same work.

Was this answer helpful?

Important Questions from Time and Work

  1. Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?

  2. A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?

  3. Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?

  4. A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?

  5. lf 12 men can do a work in 20 days, in how many days will the work be done by 15 men-
Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App