A.B and C are assigned to complete a work. If the ratio of time taken by A, B and C is 4 ∶ 3 ∶ 6. Find the ratio of their efficiency.
3 ∶ 4 ∶ 2
This question involves the relationship between time taken to complete a work and the efficiency of the individuals doing the work. For a fixed amount of work, efficiency is inversely proportional to the time taken.
When we talk about time and work, efficiency is defined as the amount of work done per unit of time. If a person takes less time to complete a certain amount of work, it means they are more efficient. Conversely, if they take more time, they are less efficient.
The relationship can be expressed as:
$$Efficiency \propto \frac{1}{Time}$$
This means that if the time taken doubles, the efficiency halves, and if the time taken halves, the efficiency doubles, assuming the total work remains constant.
We are given the ratio of time taken by A, B, and C to complete a work:
Time ratio of A : B : C = $T_A : T_B : T_C = 4 : 3 : 6$.
Since efficiency is inversely proportional to time, the ratio of their efficiencies will be the inverse ratio of their times.
Efficiency ratio of A : B : C = $E_A : E_B : E_C = \frac{1}{T_A} : \frac{1}{T_B} : \frac{1}{T_C}$
Substituting the given time ratio:
$$E_A : E_B : E_C = \frac{1}{4} : \frac{1}{3} : \frac{1}{6}$$
To express the ratio $\frac{1}{4} : \frac{1}{3} : \frac{1}{6}$ as a ratio of integers, we need to multiply each fraction by the least common multiple (LCM) of the denominators (4, 3, and 6).
Now, multiply each term in the ratio by 12:
So, the efficiency ratio of A : B : C is $3 : 4 : 2$.
Here's a quick summary of the process:
The ratio of their efficiency is $3 : 4 : 2$. This corresponds to option 1.
| Individual | Time Ratio ($T$) | Reciprocal ($1/T$) | Efficiency Ratio ($E \propto 1/T$) |
|---|---|---|---|
| A | 4 | $1/4$ | $12 \times 1/4 = 3$ |
| B | 3 | $1/3$ | $12 \times 1/3 = 4$ |
| C | 6 | $1/6$ | $12 \times 1/6 = 2$ |
| Concept | Description | Relationship |
|---|---|---|
| Work | The total task to be completed. Often considered as 1 unit or an LCM of individual times. | |
| Time | The duration taken to complete the work. | |
| Efficiency | The amount of work done per unit of time. | Efficiency = Work / Time |
| Inverse Proportion | For a fixed work, efficiency and time are inversely proportional. | Efficiency $\propto$ 1/Time |
Understanding the relationship between time and efficiency is crucial for solving various time and work problems. These concepts are frequently tested in competitive exams. Here are some related points:
A and B can do a piece of work in 18 days. B and C together can do it in 30 days. If A is twice as good a workman as C, find in how many days B alone can do the work?
Two men and 7 women can complete a work in 28 days, whereas 6 men and 16 women can do the same work in 11 days. In how many days will 5 men and 4 women, working together, complete the same work?
A man and a woman, working together can do a work in 66 days. The ratio of their working efficiencies is 3 ∶ 2. In how many days 6 men and 2 women together can do the same work?
Each one of five men independently can complete a work in 20 days. The work is started by one person. Next day one more person joins and every next day one more person joins. From the fifth day, five persons continued working as a team. In how many days, will the work be completed?
Numan does half the work as Gagan in 4/5 of the time. If together they take 16 days to complete a piece of work, then how long will it take Gagan to complete the work?