All Exams Test series for 1 year @ ₹349 only
Question

A and B together can complete a given work in 10 days. C can complete the same work alone in 15 days. In how many days can they complete the work, if all three work together?

The correct answer is

6 days

Solving Work and Time Problems: A, B, and C Working Together

This question asks us to find out how many days it will take for three individuals, A, B, and C, to complete a specific work when they work together. We are given the time taken by A and B together, and the time taken by C alone.

Understanding Work Rate

In work and time problems, the key idea is to think about the 'rate' at which work is done. The rate is the amount of work completed per unit of time (in this case, per day). If someone completes a work in 'd' days, their rate is $\frac{1}{d}$ of the work per day.

Calculating Individual and Combined Rates

We are given the following information:

  • A and B together can complete the work in 10 days.
  • C alone can complete the same work in 15 days.

From this, we can find their rates:

  • Combined rate of A and B per day = $\frac{1}{10}$ of the work.
  • Rate of C per day = $\frac{1}{15}$ of the work.
Workers Time Taken (Days) Rate per Day (Fraction of Work)
A and B Together 10 $\frac{1}{10}$
C Alone 15 $\frac{1}{15}$

Finding the Combined Rate of A, B, and C

When A, B, and C work together, their individual rates (or in this case, the combined rate of A+B and the rate of C) add up to give their total combined rate per day.

Combined rate of (A + B + C) per day = (Rate of A + B) + (Rate of C)

Combined rate of (A + B + C) per day = $\frac{1}{10} + \frac{1}{15}$

Calculating the Total Combined Rate

To add the fractions $\frac{1}{10}$ and $\frac{1}{15}$, we need to find a common denominator. The least common multiple (LCM) of 10 and 15 is 30.

$\frac{1}{10} = \frac{1 \times 3}{10 \times 3} = \frac{3}{30}$

$\frac{1}{15} = \frac{1 \times 2}{15 \times 2} = \frac{2}{30}$

Now, add the fractions:

Combined rate of (A + B + C) per day = $\frac{3}{30} + \frac{2}{30} = \frac{3 + 2}{30} = \frac{5}{30}$

Simplify the fraction:

Combined rate of (A + B + C) per day = $\frac{5}{30} = \frac{1}{6}$ of the work.

Calculating the Time Taken When Working Together

If the combined rate of A, B, and C is $\frac{1}{6}$ of the work per day, it means they complete $\frac{1}{6}$ of the work each day. To complete the whole work (which is 1 unit), the time taken is the reciprocal of their combined rate.

Time taken by (A + B + C) together = $\frac{1}{\text{Combined rate per day}}$

Time taken by (A + B + C) together = $\frac{1}{\frac{1}{6}} = 1 \times \frac{6}{1} = 6$ days.

Therefore, A, B, and C can complete the work together in 6 days.

Revision Table: Work and Time Concepts

Concept Explanation Formula
Work Rate Amount of work done per unit of time. Rate = $\frac{1}{\text{Time taken}}$
Time Taken Total time required to complete the work. Time = $\frac{1}{\text{Rate}}$
Combined Rate Sum of individual rates when multiple people work together. Rate$_{total}$ = Rate$_1$ + Rate$_2$ + ...

Additional Information: Work and Time Problem Tips

Work and time problems often involve calculating rates and combining them. Here are some useful tips:

  • Always convert the given time into a daily rate by taking the reciprocal.
  • If people work together, add their individual rates to find their combined rate.
  • If people work on different parts or have different efficiencies, adjust their rates accordingly (though not needed in this specific problem).
  • The total work is usually considered as 1 unit.
  • If units of time are different (e.g., hours and days), convert them to a common unit before calculation.
Was this answer helpful?

Important Questions from Time and Work

  1. A works thrice as fast as B. If B can complete a work in 256 days independently, then find the number of days in which A and B can together
    finish the work.
  2. A can finish a job in 146 days, B can finish the same job in 219 days and C can finish the same job in 292 days. If all three are working together, how many days will they require to complete the same job?
  3. X can finish a work in 153 days, Y can finish a work in 255 and Z can finish the same piece of work 340 days. How many days will they require to complete the work, if X, Y and Z are working together?
  4. A finish a work in 1170 days and B can do the same work in 2340 days. Working together, they will complete the same work in how many days?
  5. A can finish a job in 102 days, B can finish the same job in 153 days and C can finish the same job in 204 days. If all three are working together, how many days will they require to complete the same job?
Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App