84 men can complete a work in 30 days. After 15 days, more men were engaged, and the work was completed in 5 days ahead of schedule. How many more people were engaged in total?
42 men
Total work is \(84 \times 30 = 2520\) man-days.
In the first 15 days, work done by 84 men is \(84 \times 15 = 1260\) man-days, so the remaining work is \(2520 - 1260 = 1260\) man-days.
Since the work finishes 5 days early, the total time taken is \(30 - 5 = 25\) days, so the remaining work is completed in \(25 - 15 = 10\) days.
Men required for the remaining work: \(\frac{1260}{10} = 126\). The additional men engaged are \(126 - 84 = 42\).
A completes 80% of a work in 20 days. Then B joins A and they complete the remaining work in 3 days. How long will B alone take to complete the whole work?
A can do a piece of work in 40 days. He works at it for 10 days, and then B alone finishes the remaining work in 45 days. In how many days will A and B working together finish 75% of the same work?
Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?
A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?
Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?
A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?