All Exams Test series for 1 year @ ₹349 only
Question

84 men can complete a work in 30 days. After 15 days, more men were engaged, and the work was completed in 5 days ahead of schedule. How many more people were engaged in total?

This question was previously asked in
HTET 2025 Level 1 PRT Question Paper (5-Jul-2026)
The correct answer is

42 men

Total work is \(84 \times 30 = 2520\) man-days.

In the first 15 days, work done by 84 men is \(84 \times 15 = 1260\) man-days, so the remaining work is \(2520 - 1260 = 1260\) man-days.

Since the work finishes 5 days early, the total time taken is \(30 - 5 = 25\) days, so the remaining work is completed in \(25 - 15 = 10\) days.

Men required for the remaining work: \(\frac{1260}{10} = 126\). The additional men engaged are \(126 - 84 = 42\).

Was this answer helpful?

Similar Questions

  1. A completes 80% of a work in 20 days. Then B joins A and they complete the remaining work in 3 days. How long will B alone take to complete the whole work?

  2. A can do a piece of work in 40 days. He works at it for 10 days, and then B alone finishes the remaining work in 45 days. In how many days will A and B working together finish 75% of the same work?


Important Questions from Time and Work

  1. Surbhi can do a piece of work in 24 days. She completed 3/8 of the work and then left it. Amit can complete the remaining work in 10 days. Working together, they will complete 125% of the same work in:

  2. Rama and Hari can together finish a piece of work in 15 day. Rama works twice as fast as Hari, then Hari alone can finish work in :

  3. Anil, Deepak and Dinesh together can complete a work in 35 days. Anil and Dinesh together can complete the same work in 60 days. In how many days Deepak alone can complete the same work?

  4. Anu is four times as good as Binni in completing a task. Together they finish the same task in 7 hours. In how many hours will Anu alone complete the task?

  5. P, Q and R can complete a work in 10 days, 20 days and 30 days, respectively, working alone. How soon can the work be completed if P is assisted by Q and R on alternate days?

Need Expert Advice?
Test Series
HTET img
Teaching
HTET TGT Physical Education Mock Test Series
83 Tests 2 Tests Free
988 Attempts
4.2(9)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App