All Exams Test series for 1 year @ ₹349 only
Question

84 men can complete a work in 30 days. After 15 days, more men were engaged, and the work was completed in 5 days ahead of schedule. How many more people were engaged in total?

This question was previously asked in
HTET 2025 Level 1 PRT Question Paper (5-Jul-2026)
The correct answer is

42 men

Total work is \(84 \times 30 = 2520\) man-days.

In the first 15 days, work done by 84 men is \(84 \times 15 = 1260\) man-days, so the remaining work is \(2520 - 1260 = 1260\) man-days.

Since the work finishes 5 days early, the total time taken is \(30 - 5 = 25\) days, so the remaining work is completed in \(25 - 15 = 10\) days.

Men required for the remaining work: \(\frac{1260}{10} = 126\). The additional men engaged are \(126 - 84 = 42\).

Was this answer helpful?

Similar Questions

  1. A can do a piece of work in 40 days. He works at it for 10 days, and then B alone finishes the remaining work in 45 days. In how many days will A and B working together finish 75% of the same work?

  2. A completes 80% of a work in 20 days. Then B joins A and they complete the remaining work in 3 days. How long will B alone take to complete the whole work?


Important Questions from Time and Work

  1. A works thrice as fast as B. If B can complete a work in 256 days independently, then find the number of days in which A and B can together
    finish the work.
  2. A can finish a job in 146 days, B can finish the same job in 219 days and C can finish the same job in 292 days. If all three are working together, how many days will they require to complete the same job?
  3. X can finish a work in 153 days, Y can finish a work in 255 and Z can finish the same piece of work 340 days. How many days will they require to complete the work, if X, Y and Z are working together?
  4. A finish a work in 1170 days and B can do the same work in 2340 days. Working together, they will complete the same work in how many days?
  5. A can finish a job in 102 days, B can finish the same job in 153 days and C can finish the same job in 204 days. If all three are working together, how many days will they require to complete the same job?
Need Expert Advice?
Upcoming Exams
CTET
December 12, 2026
CBSE UGC NET
December 14, 2026
CSIR UGC NET
December 19, 2026
Test Series
HTET img
Teaching
HTET TGT Physical Education Mock Test Series
83 Tests 2 Tests Free
1017 Attempts
4.2(9)
English, Hindi
More Questions from HTET

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App