All Exams Test series for 1 year @ ₹349 only
Question

7 men can complete a piece of work in 6 days while 4 women can do it in 14 days. In how many days can 2 women and 2 men complete it?

The correct answer is

12 days

Let the amount of work done by one man in one day be m and by one woman be w.

From the given, 7 men complete the work in 6 days, so the total work is:

Work = 7 × 6 × m = 42m

Similarly, 4 women complete the work in 14 days, so the total work is:

Work = 4 × 14 × w = 56w

Thus, we have the equations:

42m = 56w

m = (56 / 42) × w = 4/3 w

Now, 2 men and 2 women complete the work in d days. The total work is:

Work = 2 × m × d + 2 × w × d

Substituting m = 4/3 w, we get:

Work = 2 × (4/3)w × d + 2 × w × d = (8/3)w × d + 2w × d

Work = w × d × (8/3 + 2) = w × d × (14/3)

Equating this with the total work (42m = 56w), we have:

w × d × (14/3) = 56w

d × (14/3) = 56

d = 56 × (3 / 14) = 12 days

Thus, 2 women and 2 men can complete the work in 12 days.

Was this answer helpful?

Important Questions from Time and Work

  1. Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?

  2. A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?

  3. Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?

  4. A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?

  5. lf 12 men can do a work in 20 days, in how many days will the work be done by 15 men-
Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App