5 th February 2018 is a Monday. 8 th April 2019 will be a:
Monday
The question asks us to determine the day of the week for April 8th, 2019, given that February 5th, 2018, was a Monday. To solve this, we need to calculate the number of days between these two dates and find the equivalent change in the day of the week.
We can approach this by first finding the day of the week exactly one year after the starting date, and then calculating the day from that point to the target date.
From February 5th, 2018, to February 5th, 2019, is exactly one year. We need to check if this period includes a leap day (February 29th).
Since neither year is a leap year and we are crossing from 2018 into 2019 on Feb 5th, the period contains 365 days.
To find the change in the day of the week, we divide the number of days by 7 (the number of days in a week) and look at the remainder:
$\text{Number of days} = 365$
$\text{Change in day} = 365 \pmod 7$
Calculating the remainder:
$365 = 52 \times 7 + 1$
The remainder is 1. This means February 5th, 2019, will be 1 day after the day of February 5th, 2018.
Since February 5th, 2018, was a Monday, February 5th, 2019, will be Tuesday.
Now we need to find the number of days from February 5th, 2019 (which is a Tuesday), to April 8th, 2019.
We sum the number of days remaining in February, plus the full month of March, plus the days in April until the 8th:
Total number of days $= 23 (\text{Feb}) + 31 (\text{Mar}) + 8 (\text{Apr})$
Total number of days $= 62$ days.
We have 62 days from February 5th, 2019, to April 8th, 2019. We find the change in the day of the week by calculating the remainder when 62 is divided by 7.
$\text{Number of days} = 62$
$\text{Change in day} = 62 \pmod 7$
Calculating the remainder:
$62 = 8 \times 7 + 6$
The remainder is 6. This means April 8th, 2019, will be 6 days after the day of February 5th, 2019.
We know that February 5th, 2019, was a Tuesday. We need to find the day 6 days after Tuesday.
So, 6 days after Tuesday is Monday.
Based on our calculations, if February 5th, 2018, was a Monday, then April 8th, 2019, will be a Monday.
| Date | Day |
|---|---|
| February 5th, 2018 | Monday |
| February 5th, 2019 (365 days later) | Monday + 1 day = Tuesday |
| April 8th, 2019 (62 days after Feb 5th, 2019) | Tuesday + 6 days = Monday |
| Concept | Description | Calculation Detail |
|---|---|---|
| Days in a week | There are 7 days in a standard week. | Used for modulo 7 operations. |
| Ordinary Year | A year with 365 days. Occurs when the year is not divisible by 4, or if divisible by 100 but not by 400. | $365 \pmod 7 = 1$. Day shifts forward by 1. |
| Leap Year | A year with 366 days (February has 29 days). Occurs when the year is divisible by 4 (except for years divisible by 100 but not by 400). | $366 \pmod 7 = 2$. Day shifts forward by 2 if Feb 29 is included. |
| Calculating Day Difference | To find the day of the week difference over a period, calculate total days and find the remainder when divided by 7. | $\text{Total Days} \pmod 7 = \text{Day Shift}$. Add shift to the starting day. |
Calculating the day of the week for a specific date, especially across years, relies on understanding calendar cycles and the concept of the odd day or day shift.
An ordinary year has 365 days. $365 = 52 \times 7 + 1$. This means an ordinary year contains 52 full weeks and 1 extra day. So, the day of the week shifts forward by 1 day for the same date in the following year, provided no leap day is crossed.
A leap year has 366 days. $366 = 52 \times 7 + 2$. This means a leap year contains 52 full weeks and 2 extra days. If the period crosses February 29th, the day of the week shifts forward by 2 days for the same date in the following year.
In our problem, going from Feb 5, 2018, to Feb 5, 2019, crosses the period after Feb 2018 and before Feb 2019. Neither 2018 nor 2019 is a leap year, so no Feb 29th is encountered in this specific annual jump. Therefore, the shift is only +1 day.
When calculating days within the same year or consecutive years, we sum the days in each month involved and then take the total modulo 7 to find the net shift. The months have different numbers of days: 31, 28/29, 31, 30, 31, 30, 31, 31, 30, 31, 30, 31. The remainders modulo 7 for these lengths are: 3, 0/1, 3, 2, 3, 2, 3, 3, 2, 3, 2, 3. This can be a quicker way to calculate the day shift over several months.
For example, the shift from Feb 5, 2019 to Apr 8, 2019:
This confirms our calculation of a 6-day shift from Feb 5th to Apr 8th within 2019.
If 19 July 2000 was a Wednesday, then what would be the day of the week on 15 June 2012?
What day of the week was 31 st January 2007?
What was the day of the week on 10 June 2011?
What day of the week was 5 February 2008?
What day of the week was 29 June 2010?