14 people can do work in 28 days. In how many days, can 8 people complete double the work?
98 days
This problem involves the concept of work and time, specifically how the number of workers affects the time taken to complete a certain amount of work. The key idea is that the total amount of "man-work" required for a specific job remains constant, assuming the efficiency of each person is the same.
We can use the relationship between the number of people (M), the number of days (D), and the amount of work (W). A common formula used for this type of problem is:
\(\frac{M_1 \times D_1}{W_1} = \frac{M_2 \times D_2}{W_2}\)
Here, the subscripts 1 and 2 refer to the two different scenarios given in the question.
We have two scenarios:
Let's define the variables for each scenario:
For the second scenario:
Now, substitute these values into the formula:
\(\frac{M_1 \times D_1}{W_1} = \frac{M_2 \times D_2}{W_2}\)
\(\frac{14 \times 28}{1} = \frac{8 \times x}{2}\)
First, simplify the equation:
\(14 \times 28 = \frac{8x}{2}\)
\(392 = 4x\)
Now, isolate \(x\) by dividing both sides by 4:
\(x = \frac{392}{4}\)
\(x = 98\)
So, 8 people can complete double the work in 98 days.
The number of days required for 8 people to complete double the work is 98 days.
| Scenario | Number of People (M) | Number of Days (D) | Amount of Work (W) |
|---|---|---|---|
| Scenario 1 | 14 | 28 | 1 |
| Scenario 2 | 8 | 98 | 2 |
| Concept | Explanation |
|---|---|
| Man-Days | The total amount of work is often measured in "man-days" (or man-hours, etc.), which is the product of the number of workers and the time they spend. Total Work = Number of Men \(\times\) Number of Days. |
| Efficiency | Assumed to be constant per person unless stated otherwise. This means each person does the same amount of work in a given time. |
| Direct Proportion | If the number of people is constant, more days mean more work completed (Work \(\propto\) Days). If the amount of work is constant, more people mean less time needed (People \(\propto \frac{1}{\text{Days}}\)). |
Work and time problems can have several variations, including:
Understanding the inverse relationship between the number of workers and the time taken for a fixed amount of work, and the direct relationship between work done and time (with fixed workers), is crucial for solving these problems.
Surbhi can do a piece of work in 24 days. She completed 3/8 of the work and then left it. Amit can complete the remaining work in 10 days. Working together, they will complete 125% of the same work in:
Rama and Hari can together finish a piece of work in 15 day. Rama works twice as fast as Hari, then Hari alone can finish work in :
Anil, Deepak and Dinesh together can complete a work in 35 days. Anil and Dinesh together can complete the same work in 60 days. In how many days Deepak alone can complete the same work?
Anu is four times as good as Binni in completing a task. Together they finish the same task in 7 hours. In how many hours will Anu alone complete the task?
P, Q and R can complete a work in 10 days, 20 days and 30 days, respectively, working alone. How soon can the work be completed if P is assisted by Q and R on alternate days?