14 people can do work in 28 days. In how many days, can 8 people complete double the work?
98 days
This problem involves the concept of work and time, specifically how the number of workers affects the time taken to complete a certain amount of work. The key idea is that the total amount of "man-work" required for a specific job remains constant, assuming the efficiency of each person is the same.
We can use the relationship between the number of people (M), the number of days (D), and the amount of work (W). A common formula used for this type of problem is:
\(\frac{M_1 \times D_1}{W_1} = \frac{M_2 \times D_2}{W_2}\)
Here, the subscripts 1 and 2 refer to the two different scenarios given in the question.
We have two scenarios:
Let's define the variables for each scenario:
For the second scenario:
Now, substitute these values into the formula:
\(\frac{M_1 \times D_1}{W_1} = \frac{M_2 \times D_2}{W_2}\)
\(\frac{14 \times 28}{1} = \frac{8 \times x}{2}\)
First, simplify the equation:
\(14 \times 28 = \frac{8x}{2}\)
\(392 = 4x\)
Now, isolate \(x\) by dividing both sides by 4:
\(x = \frac{392}{4}\)
\(x = 98\)
So, 8 people can complete double the work in 98 days.
The number of days required for 8 people to complete double the work is 98 days.
| Scenario | Number of People (M) | Number of Days (D) | Amount of Work (W) |
|---|---|---|---|
| Scenario 1 | 14 | 28 | 1 |
| Scenario 2 | 8 | 98 | 2 |
| Concept | Explanation |
|---|---|
| Man-Days | The total amount of work is often measured in "man-days" (or man-hours, etc.), which is the product of the number of workers and the time they spend. Total Work = Number of Men \(\times\) Number of Days. |
| Efficiency | Assumed to be constant per person unless stated otherwise. This means each person does the same amount of work in a given time. |
| Direct Proportion | If the number of people is constant, more days mean more work completed (Work \(\propto\) Days). If the amount of work is constant, more people mean less time needed (People \(\propto \frac{1}{\text{Days}}\)). |
Work and time problems can have several variations, including:
Understanding the inverse relationship between the number of workers and the time taken for a fixed amount of work, and the direct relationship between work done and time (with fixed workers), is crucial for solving these problems.
Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?
A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?
Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?
A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?