Question

Which one of the following is the correct estimation model based on software equation?

This question was previously asked in
UGC NET 2024 Management Question Paper (02-Sep-2024) (Shift 2)
The correct answer is

E = [LOC×B0.333/P]3 × (1/t4)

The software equation is a dynamic multivariable estimation model derived by Putnam and Myers from productivity data of thousands of projects. It assumes a specific distribution of effort over the life of a project and relates delivered size, special skills, productivity and duration.

Step 1 — The model is \(E = \left[\dfrac{\text{LOC} \times B^{0.333}}{P}\right]^{3} \times \dfrac{1}{t^{4}}\), where E is effort in person-months or person-years, t is project duration in months or years, B is a special skills factor and P is a productivity parameter.

Step 2 — B grows slowly with size (about 0.16 for 5–15 KLOC and 0.39 for programs above 70 KLOC), and P reflects process maturity and the application type (for example about 2,000 for real-time embedded software and 28,000 for business systems).

Step 3 — The cube on the bracket and the fourth power of time come from Putnam's derivation: compressing the schedule increases effort very steeply because effort varies inversely with the fourth power of duration.

The forms with exponent 0.222 squared, 0.444 to the fourth power or 0.111 to the sixth power, or with t cubed in the denominator, do not match the published equation.

E = [LOC×B0.333/P]3 × (1/t4) option is correct.

Was this answer helpful?

Similar Questions

  1. As compared to rental and leasing methods to acquire computer systems for a Management Information System (MIS), purchase method has following advantage :

  2. Which of the following is not a software process model ?

  3. Match the following for methods of MIS development :

    List - IList - II
    (a) Joint Application Design (JAD)(i) Delivers functionality in rapid iteration measured in weeks and needs frequent communication, development, testing and delivery
    (b) Computer Aided Software Engg(ii) Reusable applications generally with one specific function. It is closely linked with idea of web services and service oriented architecture.
    (c) Agile development(iii) Tools to automate many tasks of SDLC
    (d) Component based technology(iv) A group based tool for collecting user requirements and creating system design. Mostly used in analysis and design stages of SDLC

    Codes :

  4. A software design is highly modular if :

  5. A Design concept Refinement is a :

  6. Which one from the following is highly associated activity of project planning ?

  7. Cohesion is an extension of :

  8. _______ of a system is the structure or structures of the system which comprise software elements, the externally visible properties of these elements and the relationship amongst them.

  9. Which one of the following is not a risk management technique for managing the risk due to unrealistic schedules and budgets ?

  10. Match List - I with List - II.

    List - I (software design principles)List - II (Definition)
    (A) Cohesion(I) Degree to which one module relies on another module.
    (B) Coupling(II) Dividing a software system into distinct modules.
    (C) Abstration(III) Degree to which elements of a module belong together.
    (D) Modularity(IV) Simplifying complex reality by modeling classes appropriate to the problem.

    Choose the correct answer from the options given below :


Important Questions from Software Development Models

  1. A simple stand - alone software utility is to be developed in ’C’ programming by a team of software experts for a computer running Linux and the overall size of this software is estimated to be 20,000 lines of code. Considering (a, b) = (2.4, 1.05) as multiplicative and exponention factor for the basic COCOMO effort estimation equation and (c, d)=(2.5, 0.38) as multiplicative and exponention factor for the basic COCOMO development time estimation equation, approximately how long does the software project take to complete ?  

  2. In ______ model, software is developed in a series of incremental releases.

  3. In _______ model, software is developed in a series of incremental releases.

    I. Spiral

    II. Sequential

  4. Among the following, which option describes a functional requirement?

  5. A software development firm is planning a new project involving a data analytics tool. The project is estimated to have $25000$ lines of code. Using the basic COCOMO model, the firm wants to estimate the effort in person-months. For this project type, the multiplicative factor is given as $2.8$, and the exponentiation factor is $1.2$. What is the estimated effort in person-months?

Need Expert Advice?
Upcoming Exams
CTET
December 12, 2026
Test Series
UGC NET img
Teaching
UGC NET (Paper 2) 2026 Mock Test Series
796 Tests 2 Tests Free
4.4(39)
English
More Questions from UGC NET

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App