What is the duty cycle of a radar with pulse width 0.3 µs and pulse repetation rate of 1 ms ?

The correct answer is
0.0003

Radar Duty Cycle Calculation

This solution explains how to calculate the duty cycle of a radar system using its pulse width and pulse repetition rate (which we interpret as Pulse Repetition Interval, PRI, based on the units given).

Understanding Radar Duty Cycle

The duty cycle ($D$) in radar technology is defined as the ratio of the time the radar transmitter is active (transmitting a pulse) to the total time period allocated for one pulse cycle. It essentially tells us what fraction of time the radar is transmitting.

  • Mathematically, it's represented as: $ D = \frac{\text{Pulse Width (} T_p \text{)}}{\text{Pulse Repetition Interval (PRI)}} $
  • The Pulse Repetition Rate (PRR) is the number of pulses per second, while the Pulse Repetition Interval (PRI) is the time between the start of consecutive pulses. They are reciprocals: $ \text{PRR} = \frac{1}{\text{PRI}} $.
  • Since the question provides the value in milliseconds (ms), it's commonly interpreted as the Pulse Repetition Interval (PRI).

Given Information

The problem provides the following details:

  • Pulse Width ($T_p$): $ 0.3 \text{ µs} $
  • Pulse Repetition Interval (PRI): $ 1 \text{ ms} $

Step-by-Step Calculation

To find the duty cycle, follow these steps:

  1. Standardize Units: Convert both the pulse width and the PRI to the same base unit, typically seconds (s).
    • Pulse Width ($T_p$): $ 0.3 \text{ µs} = 0.3 \times 10^{-6} \text{ s} $
    • PRI: $ 1 \text{ ms} = 1 \times 10^{-3} \text{ s} $
  2. Apply the Duty Cycle Formula: Substitute the standardized values into the duty cycle equation. $ D = \frac{T_p}{\text{PRI}} $ $ D = \frac{0.3 \times 10^{-6} \text{ s}}{1 \times 10^{-3} \text{ s}} $
  3. Compute the Result: Perform the division. $ D = 0.3 \times 10^{-6 - (-3)} $ $ D = 0.3 \times 10^{-3} $ $ D = 0.0003 $

The duty cycle is a dimensionless quantity. Therefore, the calculated duty cycle for this radar is 0.0003.

Final Answer Summary

By converting the given pulse width and pulse repetition interval to seconds and applying the duty cycle formula, we find the duty cycle to be 0.0003.

Was this answer helpful?

Important Questions from Modulation

  1. An advantage of modulation is the use of _____.
  2. In an AM with m=1, the power in one sideband is:

  3. Match the following lists :

    List – IList – II  
    a. PCMi. Slope overload distortion
    b. DMii. Constant carrier frequency
    c. AMiii. Encoding
    d. TDMiv. Commutator

    The correct match is :

  4. Match the following :

    List – I  List – II
    a. DSB-SC modulationi. envelope detection
    b. SSB-modulationii. Foster Seeley
    c. AM-demodulationiii. Weaver's method
    d. Phase-shift detectioniv. Balanced modulator

    Codes :

  5.   Match the following :

    List – I List – II
    a. Power efficient transmissioni. SSB-SC
    b. Most bandwidth efficient transmission of voice signalii. VSB
    c. Simplest receiveriii. FM
    d. Bandwidth efficient transmission of signals with significant d.c. componentiv. AM

    Codes :

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App