Sanjya and Saumya together can complete a work in 9 days. Sanjya alone can do the same work in 15 days. In how many days can Saumya alone do the same work?
\( 22\frac{1}{2} \) days
One day's work of (Sanjya + Saumya) = 1/9; one day's work of Sanjya = 1/15.
Saumya's one day's work = 1/9 - 1/15
= (5 - 3)/45
= 2/45
Time taken by Saumya alone = 45/2 = 22.5 days
Hence, \( 22\frac{1}{2} \) days.
A, B and C together can do a work in \(4\text{ days}\). If A and B can do the work in \(5\text{ days}\) and B and C in \(10\text{ days}\), then find the days taken by A and C to do the work.
A and B can do a work in \(10\) and \(15\text{ days}\) respectively. If they work on alternate days in this, A starts first. Then the work will be completed in how many days?
A and B can do a work in 15 days, B and C can do the same work in 20 days. If A is twice as good a worker as C, then find the time which C alone will take to do the work.
Raju and Vinod are working on an assignment. Raju takes 8h to type 32 pages on a computer, while Vinod takes 6h to type 44 pages. How much time will they take, working together, to type an assignment of 102 pages on two different computers?
A can do a certain work in the same time in which B and C together can do it. If A and B together can do it in 8 days and C alone can do it in 40 days, then in how many days can B alone do it?
A can do a work in 10 days and B in 15 days. If they work together for 5 days, what fraction of the work will be left?
A can do a work in 3 hours. B and C together can do it in 4 hours, while A and C together can do it in 2 hours. How much time will B alone take to do it?
15 people can complete a work in 8 days. How many more people are needed to complete the double work in 12 days?
A and B can complete a work in 15 days, while A, B and C can complete it in 10 days. How much time will C take to complete the work alone?
If 10 men working 6 hours a day can complete a work in 90 days, then in how many days can 6 men working 15 hours a day complete that work?
A person can complete 20% of work in 8 days and another person y can complete 25% of the same work in 6 days. If they work together, in how many days will 40% of the work be completed?
P works thrice as fast as Q, whereas P and Q together can work four times as fast as R. If P, Q and R together work on a job, in what ratio should they share the earnings?
There are three pillars X, Y and Z of different heights. Three spiders A, B and C start to climb on these pillars simultaneously. In one chance, A climbs on X by 6 cm but slips down 1 cm. B climbs on Y by 7 cm but slips down 3 cm. C climbs on Z by 6.5 cm but slips down 2 cm. If each of them requires 40 chances to reach the top of the pillars, what is the height of the shortest pillar?
There is an order of 19000 quantity of a particular product from a customer. The firm produces 1000 quantity of that product per out of which 5% are unfit for sale. In how many days will the order be completed?
Ram and Shyam work on a job together for four days and complete 60% of it. Ram takes leave then and Shyam works for eight more days to complete the job. How long would Ram take to complete the entire job alone?