A and B can do a work in \(10\) and \(15\text{ days}\) respectively. If they work on alternate days in this, A starts first. Then the work will be completed in how many days?
\(12\text{ days}\)
12 days is correct.
In alternate-day work, find the work done in one complete two-day cycle and count how many cycles are needed.
One-day work: A \(= \dfrac{1}{10}\), B \(= \dfrac{1}{15}\).
Each two-day cycle (A then B) completes \(\dfrac{1}{10} + \dfrac{1}{15} = \dfrac{3 + 2}{30} = \dfrac{1}{6}\) of the work.
The whole work needs \(6\) such cycles, i.e. \(6 \times 2 = 12\) days, ending exactly on B's day.
A, B and C together can do a work in \(4\text{ days}\). If A and B can do the work in \(5\text{ days}\) and B and C in \(10\text{ days}\), then find the days taken by A and C to do the work.
If 5 girls can embroider a dress in 9 days, then in how many days will 3 girls do the same work?
A and B can do a work in 4 days and C and D can do it in 3 days. In how many days can A, B, C and D do it together?
A can complete a work in 8 days, B can complete the same work in 10 days and C can complete it in 12 days. In how many days can they complete the work together?
If A can complete a work in 30 days and B can complete the same work in 20 days, then in how many days will A and B together complete the same work?
60 boys working 7 hours a day can complete a piece of work in 18 days. In how many days will 28 boys working 9 hours a day complete the same work?
A alone can do a piece of work in 6 days, B and C together in 4 days, and A and C together in 3 days. Then in how many days will B complete the work?
If 12 women can complete a work in 20 days working 8 hours a day, then how many hours a day will 16 women have to work to complete the same work in 15 days?
Meena can complete a work in 10 days, while Meena and Reena together can complete the same work in 7 days. How much time will Reena take to complete the work alone?
15 people can complete a work in 8 days. How many more people are needed to complete the double work in 12 days?
A person can complete 20% of work in 8 days and another person y can complete 25% of the same work in 6 days. If they work together, in how many days will 40% of the work be completed?
P works thrice as fast as Q, whereas P and Q together can work four times as fast as R. If P, Q and R together work on a job, in what ratio should they share the earnings?
There are three pillars X, Y and Z of different heights. Three spiders A, B and C start to climb on these pillars simultaneously. In one chance, A climbs on X by 6 cm but slips down 1 cm. B climbs on Y by 7 cm but slips down 3 cm. C climbs on Z by 6.5 cm but slips down 2 cm. If each of them requires 40 chances to reach the top of the pillars, what is the height of the shortest pillar?
There is an order of 19000 quantity of a particular product from a customer. The firm produces 1000 quantity of that product per out of which 5% are unfit for sale. In how many days will the order be completed?
Ram and Shyam work on a job together for four days and complete 60% of it. Ram takes leave then and Shyam works for eight more days to complete the job. How long would Ram take to complete the entire job alone?