This question involves a concept known as inverse proportion. When the amount of work is constant, the number of workers and the time taken to complete the job are inversely related. This means if you increase the number of workers, the time required to finish the job decreases, and vice versa.
First, we need to determine the total amount of work required to complete the job. This is often measured in "worker-days," which represents the total effort needed.
The total work can be calculated as:
Total Work = Number of Workers \(\times\) Time Taken
Total Work = \(4 \text{ workers} \times 12 \text{ days} = 48 \text{ worker-days}\)
Now, we know the total work required is 48 worker-days. We need to find out how many days it will take for 6 workers to complete this same amount of work.
Using the same formula for total work:
Total Work = Number of Workers \(\times\) Time Taken
\(48 \text{ worker-days} = 6 \text{ workers} \times D \text{ days}\)
To find the value of '\(D\)', we rearrange the equation:
\(D = \frac{\text{Total Work}}{\text{Number of workers (new)}}\)
\(D = \frac{48 \text{ worker-days}}{6 \text{ workers}}\)
\(D = 8 \text{ days}\)
Therefore, 6 workers will take 8 days to complete the same job.
A person can complete 20% of work in 8 days and another person y can complete 25% of the same work in 6 days. If they work together, in how many days will 40% of the work be completed?
P works thrice as fast as Q, whereas P and Q together can work four times as fast as R. If P, Q and R together work on a job, in what ratio should they share the earnings?
There are three pillars X, Y and Z of different heights. Three spiders A, B and C start to climb on these pillars simultaneously. In one chance, A climbs on X by 6 cm but slips down 1 cm. B climbs on Y by 7 cm but slips down 3 cm. C climbs on Z by 6.5 cm but slips down 2 cm. If each of them requires 40 chances to reach the top of the pillars, what is the height of the shortest pillar?
There is an order of 19000 quantity of a particular product from a customer. The firm produces 1000 quantity of that product per out of which 5% are unfit for sale. In how many days will the order be completed?
Ram and Shyam work on a job together for four days and complete 60% of it. Ram takes leave then and Shyam works for eight more days to complete the job. How long would Ram take to complete the entire job alone?