The question asks for the total time required to complete a job when two individuals, A and B, work together. We are given the individual times each person takes to complete the job alone.
We need to find the time it takes when they collaborate.
To solve this, we first determine the rate at which each person works. The rate is the fraction of the job completed per day.
When A and B work together, their individual rates add up to give the combined rate of work.
Combined Rate = Rate of A + Rate of B
Combined Rate = \(\frac{1}{10} + \frac{1}{15}\)
To add these fractions, we find a common denominator, which is 30.
Combined Rate = \(\frac{3}{30} + \frac{2}{30}\)
Combined Rate = \(\frac{3+2}{30}\)
Combined Rate = \(\frac{5}{30}\)
Simplifying the fraction, we get:
Combined Rate = \(\frac{1}{6}\) job per day.
This means that working together, A and B complete \(\frac{1}{6}\) of the job each day.
The total time taken to complete the job when working together is the reciprocal of their combined work rate.
Time Together = \(\frac{1}{\text{Combined Rate}}\)
Time Together = \(\frac{1}{\frac{1}{6}}\)
Time Together = 6 days.
Therefore, if A and B work together, they will take 6 days to complete the job.
A person can complete 20% of work in 8 days and another person y can complete 25% of the same work in 6 days. If they work together, in how many days will 40% of the work be completed?
P works thrice as fast as Q, whereas P and Q together can work four times as fast as R. If P, Q and R together work on a job, in what ratio should they share the earnings?
There are three pillars X, Y and Z of different heights. Three spiders A, B and C start to climb on these pillars simultaneously. In one chance, A climbs on X by 6 cm but slips down 1 cm. B climbs on Y by 7 cm but slips down 3 cm. C climbs on Z by 6.5 cm but slips down 2 cm. If each of them requires 40 chances to reach the top of the pillars, what is the height of the shortest pillar?
There is an order of 19000 quantity of a particular product from a customer. The firm produces 1000 quantity of that product per out of which 5% are unfit for sale. In how many days will the order be completed?
Ram and Shyam work on a job together for four days and complete 60% of it. Ram takes leave then and Shyam works for eight more days to complete the job. How long would Ram take to complete the entire job alone?