This problem requires us to calculate the total duration needed to finish a job based on individual work speeds and a specific work schedule. We need to find the total days until the job is fully completed.
Key concepts for solving this type of problem:
We first determine the rate at which A and B work individually:
A starts the job and works alone for 3 days. Let's calculate the fraction of the job A completes during this period:
Work done by A = (A's daily rate) $\times$ (Number of days A worked alone)
Work done by A = $\frac{1}{12} \times 3$
Work done by A = $\frac{3}{12} = \frac{1}{4}$
After 3 days, $1/4$ of the job is completed by A.
The next step is to find out how much of the job is left after A's initial work:
Remaining Work = Total Work - Work done by A
Remaining Work = $1 - \frac{1}{4}$
Remaining Work = $\frac{3}{4}$
So, $3/4$ of the job still needs to be completed.
From the 4th day, A and B work together. To find the time they take together, we first calculate their combined daily work rate:
Combined Rate = A's Rate + B's Rate
Combined Rate = $\frac{1}{12} + \frac{1}{18}$
Find the least common multiple (LCM) of 12 and 18, which is 36, to add the fractions:
Combined Rate = $\frac{3}{36} + \frac{2}{36}$
Combined Rate = $\frac{5}{36}$
When working together, A and B complete $5/36$ of the job each day.
We can now calculate the number of days A and B will take to complete the remaining $3/4$ of the job working together:
Time = Remaining Work / Combined Rate
Time = $\frac{3/4}{5/36}$
To divide fractions, we multiply by the reciprocal of the divisor:
Time = $\frac{3}{4} \times \frac{36}{5}
Time = $\frac{3 \times 36}{4 \times 5} = \frac{108}{20}
Simplifying the fraction:
Time = $\frac{27}{5}$ days
As a decimal, this is $5.4$ days.
The total time to finish the job is the sum of the initial days A worked alone and the days A and B worked together:
Total Days = Days A worked alone + Days A and B worked together
Total Days = $3 + 5.4$
Total Days = $8.4$ days.
The calculation indicates that the job will be completed in $8.4$ days.
Comparing this result to the options:
The calculated total time is $8.4$ days. Option 1 (8 days) is the closest provided choice.
A person can complete 20% of work in 8 days and another person y can complete 25% of the same work in 6 days. If they work together, in how many days will 40% of the work be completed?
P works thrice as fast as Q, whereas P and Q together can work four times as fast as R. If P, Q and R together work on a job, in what ratio should they share the earnings?
There are three pillars X, Y and Z of different heights. Three spiders A, B and C start to climb on these pillars simultaneously. In one chance, A climbs on X by 6 cm but slips down 1 cm. B climbs on Y by 7 cm but slips down 3 cm. C climbs on Z by 6.5 cm but slips down 2 cm. If each of them requires 40 chances to reach the top of the pillars, what is the height of the shortest pillar?
There is an order of 19000 quantity of a particular product from a customer. The firm produces 1000 quantity of that product per out of which 5% are unfit for sale. In how many days will the order be completed?
Ram and Shyam work on a job together for four days and complete 60% of it. Ram takes leave then and Shyam works for eight more days to complete the job. How long would Ram take to complete the entire job alone?