'Cover block' is used as a building construction component in

The correct answer is
RC beam

RC Beam Construction Uses Cover Blocks

A 'cover block' is a critical component specifically used in reinforced concrete (RC) construction. Its primary function is to maintain a minimum concrete thickness, known as the concrete cover, between the reinforcing steel bars (rebar) and the outer surface of the concrete element.

Function of Cover Blocks in RC Beams

In RC beams, cover blocks are placed strategically around the rebar cage before the concrete is poured. This ensures:

  • Corrosion Protection: Adequate cover protects the steel reinforcement from moisture and atmospheric agents, preventing rust and maintaining structural integrity.
  • Fire Resistance: The concrete cover acts as insulation, protecting the steel from excessive heat during a fire.
  • Structural Bond: Proper cover ensures a good bond between the concrete and the rebar.

Without cover blocks, the rebar might sit too close to the formwork, resulting in insufficient or uneven cover after pouring, compromising the beam's durability and safety.

Why Other Options Are Incorrect

The other options do not typically require cover blocks because they are not constructed using reinforced concrete in the same manner as an RC beam:

  • Brick wall: Primarily uses bricks and mortar; reinforcement, if used, is different and doesn't require cover blocks in the same way.
  • Curtain wall: This is often a non-structural building facade (e.g., glass and metal panels) and does not involve the internal reinforcement system that necessitates cover blocks.
  • Steel truss: A structural framework made of steel members, not concrete, and therefore does not use concrete cover blocks.

Therefore, the 'cover block' is fundamentally a building construction component used in RC beams.

Was this answer helpful?

Important Questions from Building Construction Techniques

  1. Match the Elements in Group - I with their Applications in Group - II
    Group - IGroup - II
    P Bracket1 Door
    Q Baluster2 Dome
    R Key stone3 Cornice
    S Holdfast4 Arch
    5 Staircase
  2. Match the Vibrator Types in Group-I with their related Areas of Application in Group-II
    Group-IGroup-II
    P Needle Vibrator1 Concrete Pavement
    Q Shutter Vibrator2 Pre-cast Concrete Unit
    R Surface Vibrator3 Beam-Column Junction
    S Table Vibrator4 Retaining Wall
    5 Slip Forming
  3. Match the type of Temporary Structures in Group - I with their corresponding Functions in Group - II
    Group-IGroup-II
    P Scaffolding1 To support unsafe structure
    Q Formwork2 To support platforms for workmen and materials at raised height during construction
    R Shoring3 Removal of water from pits
    S Underpinning4 Mould for RCC Structure
    5 Strengthening the existing foundation
  4. The number of standard cement bags required to prepare 1400 kg of concrete in the ratio of 1:2:4 (mixed by weight batching) is _______________

  5. An element constructed at intervals along the length of a wall to stabilize it against overturning is