Question

A project manager is preparing a cost estimate for a new wiring installation. The estimate accounts for materials, labor, overhead, and profit. Which method best ensures the project stays financially secure if unexpected price increases or additional work occur?

This question was previously asked in
RRB ALP 2025 CBT 2 Wiremen Question Paper (28-Jul-2026) (Shift 2)
The correct answer is

Including an appropriate contingency allowance in the estimate

A cost estimate for a wiring installation is built up from materials, labour, overhead and profit, but no estimate can perfectly predict every future condition on a live project.

Prices of copper, cable and fittings can rise, and extra unplanned work can appear once the job starts, both of which push actual cost above the original figure.

To stay financially secure against these uncertainties, an appropriate contingency allowance is added, a deliberate reserve amount built into the estimate to absorb such risks.

This reserve lets the project accommodate price increases or additional work without breaching the sanctioned budget or eroding the profit.

Excluding the contingency leaves no cushion, so any overrun directly turns into a loss on the job.

Relying only on historical cost data assumes the past repeats exactly and misses today's price movements, while ignoring potential risks simply pretends the uncertainty does not exist; neither protects the budget.

Hence, the answer is Including an appropriate contingency allowance in the estimate.

Was this answer helpful?

Similar Questions

  1. While selecting an institute for training a licensed wireman, which factor should be prioritized to ensure eligibility for the wireman permit?

  2. Which type of centrally monitored fire detection and alarm system is used in large commercial public buildings for fire safety?

  3. When an electric vehicle is connected to a charging station, which process ensures that only authorized users can access charging services securely and efficiently?

  4. An industrial PLC control panel requires compliance with electromagnetic compatibility (EMC) standards. Which design change best enhances EMC performance?


Important Questions from Miscellaneous

  1. Which of the following is NOT a state function or state variable in a thermodynamic system?

  2. What is the full form for "BPL" in Socio-economic aspects?
  3. In October 2024, which of the following companies was awarded the contract for design, manufacturing and commissioning of two high-speed trainsets by Integral Coach Factory (ICF) to be used in India's first bullet train between Mumbai and Ahmedabad?
  4. Which of the following methods of reproduction simply involves the splitting of the parent cell into two daughter cells in the bacteria?
  5. A, B, C and D opened shopping complexes in the same city. The shopping complex of A is 6 km west of the shopping complex of B. The shopping complex of C is 4 km north of the shopping complex of B. The shopping complex of D is 6 km west of the shopping complex of C. In which direction is the shopping complex of D from the shopping complex of A?
Need Expert Advice?
Test Series
RRB ALP img
Railways
RRB ALP 2026 Mock Test series
1035 Tests 1 Tests Free
1815 Attempts
4.3(260)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App