All Exams Test series for 1 year @ ₹349 only
Question

X can finish a job in $141$ days. He worked for $57$ days alone and the remaining work was completed by Y, in $84$ days. How many days would both together take to complete the entire job?

The correct answer is
70.5

Calculating Combined Job Completion Time

The problem asks for the total time X and Y would take to complete a job together. We are given information about X's individual capacity and how X and Y shared the work.

Understanding Work Rates

First, let's determine the work rate of X. If X can finish the entire job in $141$ days, then in one day, X completes:

$ \text{X's Rate} = \frac{1}{141} \text{ of the job per day} $

Work Done by X Alone

X worked alone for $57$ days. The portion of the job completed by X during this time is:

$ \text{Work by X} = \text{X's Rate} \times \text{Days worked} = \frac{1}{141} \times 57 = \frac{57}{141} $

Simplifying the fraction:

$ \frac{57}{141} = \frac{3 \times 19}{3 \times 47} = \frac{19}{47} $

So, X completed $19/47$ of the job.

Remaining Work and Y's Rate

The remaining work that needed to be completed is:

$ \text{Remaining Work} = 1 - \text{Work by X} = 1 - \frac{19}{47} = \frac{47 - 19}{47} = \frac{28}{47} $

This remaining work ($28/47$) was completed by Y in $84$ days. Therefore, Y's work rate is:

$ \text{Y's Rate} = \frac{\text{Remaining Work}}{\text{Days worked by Y}} = \frac{28/47}{84} = \frac{28}{47 \times 84} $

Simplifying Y's rate:

$ \text{Y's Rate} = \frac{28}{47 \times 3 \times 28} = \frac{1}{47 \times 3} = \frac{1}{141} \text{ of the job per day} $

Combined Work Rate

Now, we find the combined rate at which X and Y work together:

$ \text{Combined Rate} = \text{X's Rate} + \text{Y's Rate} = \frac{1}{141} + \frac{1}{141} = \frac{2}{141} \text{ of the job per day} $

Total Time for Combined Effort

The total time required for both X and Y to complete the job together is the inverse of their combined rate:

$ \text{Time Together} = \frac{\text{Total Work}}{\text{Combined Rate}} = \frac{1}{2/141} = \frac{141}{2} \text{ days} $

Calculating the final value:

$ \frac{141}{2} = 70.5 \text{ days} $

Both X and Y together would take $70.5$ days to complete the entire job.

Was this answer helpful?

Important Questions from Time & Work (Notes)

  1. A fresh water tap fills a fish tank in 40 minutes. The same tank is filled by a salt water tap in 120 minutes. If both the taps are open, how many minutes will it take to fill the tank?
  2. A completes $\frac{7}{10}$ of a work in 15 days and then he completes the remaining work with the help of B in 5 days. In how many days can A and B together complete the entire work?
  3. Aman can do 50% of the job in 16 days, and Bhanu can do 25% of the job in 24 days. In how many days can they do $\frac{1}{4}^{th}$  of the job working together ?

  4. Three workers A, B, C can finish a job in 10, 15, and 20 hours respectively. A and B start; after 2 hours, C joins and they finish the remaining work in t more hours. What is the value of t? (Rounded off to the nearest integer.)
  5. Ravina, Sujata, and Saroj can complete a work of painting separately in 32, 48, and 64 hours, respectively. They started working together, but Saroj left after 5 hours. From the 6th hour, Ravina and Sujata decided to work on alternate hours starting with Ravina. In how much time will the entire work of painting be completed?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App