This problem involves calculating the time it takes for two people, A and B, to complete a work together. We need to determine their combined efficiency based on the information given about A's individual work and their joint effort on the remaining part.
We are given that A completes $\frac{7}{10}$ of the work in 15 days. The work rate is the amount of work done per day.
A's Work Rate ($R_A$) = $\frac{\text{Work Done}}{\text{Time Taken}}$
Using LaTeX for the calculation:
$R_A = \frac{7/10}{15} = \frac{7}{10 \times 15} = \frac{7}{150} \text{ work per day}$This means A completes $\frac{7}{150}$ of the total work each day.
After A completes $\frac{7}{10}$ of the work, we need to find out how much work is left.
Remaining Work = Total Work - Work Done by A
Remaining Work = $1 - \frac{7}{10}$
Using LaTeX:
$ \text{Remaining Work} = 1 - \frac{7}{10} = \frac{10}{10} - \frac{7}{10} = \frac{3}{10} $So, $\frac{3}{10}$ of the work is remaining.
The problem states that A and B together complete this remaining work ($\frac{3}{10}$) in 5 days.
Combined Work Rate ($R_A + R_B$) = $\frac{\text{Remaining Work}}{\text{Time Taken}}$
Using LaTeX:
$ R_A + R_B = \frac{3/10}{5} = \frac{3}{10 \times 5} = \frac{3}{50} \text{ work per day} $This is the rate at which A and B work together.
We want to find the total time required for A and B, working together, to complete the entire work (1 unit). We use their combined work rate calculated in the previous step.
Time = $\frac{\text{Total Work}}{\text{Combined Work Rate}}$
Using LaTeX:
$ \text{Time}_{A+B} = \frac{1}{R_A + R_B} = \frac{1}{3/50} $ $ \text{Time}_{A+B} = \frac{50}{3} \text{ days} $To express the answer in a more common format, we convert the improper fraction $\frac{50}{3}$ into a mixed number.
Divide 50 by 3:
$ 50 \div 3 = 16 \text{ with a remainder of } 2 $Therefore, the time taken is $16\frac{2}{3}$ days.
Aman can do 50% of the job in 16 days, and Bhanu can do 25% of the job in 24 days. In how many days can they do $\frac{1}{4}^{th}$ of the job working together ?