All Exams Test series for 1 year @ ₹349 only
Question

Team A can complete a job in 15 days and Team B in 20 days. They work together for 6 days, then Team A works alone for 3 days, after which Team A's efficiency reduces to 60% while Team B joins again at 120% efficiency. How many more days will it take to complete the job?

The correct answer is
1 day

Team A and Team B Work Rates

We start by calculating the individual work rates of Team A and Team B, assuming the total job is 1 unit of work.

  • Team A's Rate ($R_A$): Completes the job in 15 days, so $R_A = \frac{1}{15}$ job/day.
  • Team B's Rate ($R_B$): Completes the job in 20 days, so $R_B = \frac{1}{20}$ job/day.

Work Calculation Phase 1: Joint Work

Teams A and B work together for 6 days. Their combined rate is:

$R_{A+B} = R_A + R_B = \frac{1}{15} + \frac{1}{20}$

To add these, we find a common denominator, which is 60:

$R_{A+B} = \frac{4}{60} + \frac{3}{60} = \frac{7}{60}$ job/day.

Work done in these 6 days ($W_1$) is calculated as:

$W_1 = \text{Combined Rate} \times \text{Time} = \frac{7}{60} \times 6 = \frac{7}{10}$ job.

Work Calculation Phase 2: Team A Alone

Team A works alone for the next 3 days. The work done during this phase ($W_2$) is:

$W_2 = R_A \times \text{Time} = \frac{1}{15} \times 3 = \frac{3}{15} = \frac{1}{5}$ job.

Total Work Done and Remaining Job

The total amount of work completed after these two phases is the sum of $W_1$ and $W_2$:

Total Work Done = $W_1 + W_2 = \frac{7}{10} + \frac{1}{5}$

Using a common denominator of 10:

Total Work Done = $\frac{7}{10} + \frac{2}{10} = \frac{9}{10}$ job.

The remaining work required to finish the job is:

Remaining Work = Total Job - Total Work Done = $1 - \frac{9}{10} = \frac{1}{10}$ job.

Efficiency Changes for Phase 3

In the final phase, the teams' work efficiencies change:

  • Team A's efficiency reduces to 60% of its original rate. The new rate ($R_{A\_new}$) is:

    $R_{A\_new} = 0.60 \times R_A = \frac{6}{10} \times \frac{1}{15} = \frac{3}{5} \times \frac{1}{15} = \frac{1}{5} \times \frac{1}{5} = \frac{1}{25}$ job/day.

  • Team B's efficiency increases to 120% of its original rate. The new rate ($R_{B\_new}$) is:

    $R_{B\_new} = 1.20 \times R_B = \frac{12}{10} \times \frac{1}{20} = \frac{6}{5} \times \frac{1}{20} = \frac{3}{5} \times \frac{1}{10} = \frac{3}{50}$ job/day.

Days Calculation for Remaining Job

Now, both teams work together again with their modified rates. Their combined rate for this phase ($R_{Phase3}$) is:

$R_{Phase3} = R_{A\_new} + R_{B\_new} = \frac{1}{25} + \frac{3}{50}$

Using a common denominator of 50:

$R_{Phase3} = \frac{2}{50} + \frac{3}{50} = \frac{5}{50} = \frac{1}{10}$ job/day.

The time needed to complete the remaining $\frac{1}{10}$ job is calculated by dividing the remaining work by the combined rate:

Time = $\frac{\text{Remaining Work}}{R_{Phase3}} = \frac{1/10 \text{ job}}{1/10 \text{ job/day}} = 1$ day.

Therefore, it will take exactly 1 more day to complete the job.

Was this answer helpful?

Important Questions from Time & Work (Notes)

  1. A fresh water tap fills a fish tank in 40 minutes. The same tank is filled by a salt water tap in 120 minutes. If both the taps are open, how many minutes will it take to fill the tank?
  2. A completes $\frac{7}{10}$ of a work in 15 days and then he completes the remaining work with the help of B in 5 days. In how many days can A and B together complete the entire work?
  3. Aman can do 50% of the job in 16 days, and Bhanu can do 25% of the job in 24 days. In how many days can they do $\frac{1}{4}^{th}$  of the job working together ?

  4. X can finish a job in $141$ days. He worked for $57$ days alone and the remaining work was completed by Y, in $84$ days. How many days would both together take to complete the entire job?
  5. Ravina, Sujata, and Saroj can complete a work of painting separately in 32, 48, and 64 hours, respectively. They started working together, but Saroj left after 5 hours. From the 6th hour, Ravina and Sujata decided to work on alternate hours starting with Ravina. In how much time will the entire work of painting be completed?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App