We start by calculating the individual work rates of Team A and Team B, assuming the total job is 1 unit of work.
Teams A and B work together for 6 days. Their combined rate is:
$R_{A+B} = R_A + R_B = \frac{1}{15} + \frac{1}{20}$
To add these, we find a common denominator, which is 60:
$R_{A+B} = \frac{4}{60} + \frac{3}{60} = \frac{7}{60}$ job/day.
Work done in these 6 days ($W_1$) is calculated as:
$W_1 = \text{Combined Rate} \times \text{Time} = \frac{7}{60} \times 6 = \frac{7}{10}$ job.
Team A works alone for the next 3 days. The work done during this phase ($W_2$) is:
$W_2 = R_A \times \text{Time} = \frac{1}{15} \times 3 = \frac{3}{15} = \frac{1}{5}$ job.
The total amount of work completed after these two phases is the sum of $W_1$ and $W_2$:
Total Work Done = $W_1 + W_2 = \frac{7}{10} + \frac{1}{5}$
Using a common denominator of 10:
Total Work Done = $\frac{7}{10} + \frac{2}{10} = \frac{9}{10}$ job.
The remaining work required to finish the job is:
Remaining Work = Total Job - Total Work Done = $1 - \frac{9}{10} = \frac{1}{10}$ job.
In the final phase, the teams' work efficiencies change:
$R_{A\_new} = 0.60 \times R_A = \frac{6}{10} \times \frac{1}{15} = \frac{3}{5} \times \frac{1}{15} = \frac{1}{5} \times \frac{1}{5} = \frac{1}{25}$ job/day.
$R_{B\_new} = 1.20 \times R_B = \frac{12}{10} \times \frac{1}{20} = \frac{6}{5} \times \frac{1}{20} = \frac{3}{5} \times \frac{1}{10} = \frac{3}{50}$ job/day.
Now, both teams work together again with their modified rates. Their combined rate for this phase ($R_{Phase3}$) is:
$R_{Phase3} = R_{A\_new} + R_{B\_new} = \frac{1}{25} + \frac{3}{50}$
Using a common denominator of 50:
$R_{Phase3} = \frac{2}{50} + \frac{3}{50} = \frac{5}{50} = \frac{1}{10}$ job/day.
The time needed to complete the remaining $\frac{1}{10}$ job is calculated by dividing the remaining work by the combined rate:
Time = $\frac{\text{Remaining Work}}{R_{Phase3}} = \frac{1/10 \text{ job}}{1/10 \text{ job/day}} = 1$ day.
Therefore, it will take exactly 1 more day to complete the job.
Three pipes A, B and C can fill a tank in $10$, $15$ and $20$ hours respectively. Pipe A was opened at $6$ AM, pipe B at $7$ AM and pipe C at $8$ AM. At what time was the tank completely filled, if pipe C needs a break of $1$ hour after remaining open for $3$ hours?
A tank has four pipes $P_1$, $P_2$, $P_3$ and $P_4$. The tank can be filled in $15$ minutes by pipes $P_1$, $P_2$, $P_3$ together. It can be filled in $20$ minutes by pipes $P_2$, $P_3$, $P_4$ together and it can be filled by pipes $P_1$, $P_4$ together in $30$ minutes. If all the pipes are opened together, then in how much time will the tank be filled?
$5$ men and $4$ women can earn ₹ $20000$ in $8$ days. $10$ men and $7$ women can earn ₹ $23,750$ in $5$ days. In how many days will $5$ men and $6$ women earn ₹ $12,000$?