Mike, Connor and Floyd can finish a certain piece of work in 8, 22 and 33 days, respectively. All three of them started the work together. Mike left the work after 4 days and Connor left just 2 days before the work was completed. Find the total number of days taken for the work to be completed.
7.8
Mike works 4 days at rate \(\tfrac18\), contributing \(4\times\tfrac18=\tfrac12\) of the work.
Let total days be T. Connor works \((T-2)\) days at rate \(\tfrac1{22}\), and Floyd works T days at rate \(\tfrac1{33}\).
Total work: \(\tfrac12 + \dfrac{T-2}{22} + \dfrac{T}{33} = 1\).
Multiplying through by 66: \(33 + 3(T-2) + 2T = 66 \Rightarrow 5T + 27 = 66 \Rightarrow T = 7.8\).
Hence, the total work takes 7.8 days to complete.
A and B can do a piece of work in 18 days. B and C together can do it in 30 days. If A is twice as good a workman as C, find in how many days B alone can do the work?
Two men and 7 women can complete a work in 28 days, whereas 6 men and 16 women can do the same work in 11 days. In how many days will 5 men and 4 women, working together, complete the same work?
A man and a woman, working together can do a work in 66 days. The ratio of their working efficiencies is 3 ∶ 2. In how many days 6 men and 2 women together can do the same work?
Each one of five men independently can complete a work in 20 days. The work is started by one person. Next day one more person joins and every next day one more person joins. From the fifth day, five persons continued working as a team. In how many days, will the work be completed?
Numan does half the work as Gagan in 4/5 of the time. If together they take 16 days to complete a piece of work, then how long will it take Gagan to complete the work?