This problem involves calculating the time taken by individuals to complete work, both individually and together. We need to find out how long Deven would take to finish the work alone.
First, determine the rate at which Lalit and Laxman complete the work individually.
Next, calculate the combined work rate when Lalit and Laxman work together and the amount of work they complete in $5$ days.
Determine the amount of work left after Lalit and Laxman have worked for $5$ days.
The remaining work ($ \frac{7}{15} $) is completed by Lalit and Deven in $4$ days. We need to find Deven's individual time.
Therefore, Deven can finish the work alone in $20\text{ days}$.
A and B can complete a task together in 12 days, while B and C can finish it in 16 days. After A works on it for 5 days and B for 7 days, C takes the remaining 13 days to finish the work. How many days would it take for C to complete the work alone?
A is three times more efficient as a worker than B, which allows A to complete a job in 60 days less than B. If they work together, they can finish the job in:
A and B can finish a certain job in 28 and 35 days, respectively. They started working together, but A left after a while, and B managed to complete the remaining work in 17 days. How many days did A work before leaving?
If 6 machines complete a task in 10 days, how many days for 15 machines at the same rate?
A can do a work in 8 days and B in 12 days. They work together for 3 days. What part of the work is left?
Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?
A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?
Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?
A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?