All Exams Test series for 1 year @ ₹349 only
Question

Lalit can finish a work in $15\text{ days}$. Laxman can finish the same work in $25\text{ days}$. They work together for $5\text{ days}$. If the rest of the work is finished by Lalit and Deven in $4\text{ days}$, then in how many days can Deven alone finish the work?

This question was previously asked in
SSC CGL 2025 Tier 1 Question Paper (25-Sep-2025) (Shift 3)
The correct answer is
$20\text{ days}$

Solving the Work and Time Problem

This problem involves calculating the time taken by individuals to complete work, both individually and together. We need to find out how long Deven would take to finish the work alone.

Calculating Individual Work Rates

First, determine the rate at which Lalit and Laxman complete the work individually.

  • Lalit's time to finish work = $15\text{ days}$.
  • Lalit's work rate = $ \frac{1}{15} $ of the work per day.
  • Laxman's time to finish work = $25\text{ days}$.
  • Laxman's work rate = $ \frac{1}{25} $ of the work per day.

Work Done Together

Next, calculate the combined work rate when Lalit and Laxman work together and the amount of work they complete in $5$ days.

  • Combined work rate of Lalit and Laxman = $ \frac{1}{15} + \frac{1}{25} $.
  • To add these fractions, find a common denominator, which is $75$.
  • Combined rate = $ \frac{5}{75} + \frac{3}{75} = \frac{8}{75} $ of the work per day.
  • Work done by Lalit and Laxman in $5$ days = $ \text{Rate} \times \text{Time} = \frac{8}{75} \times 5 $.
  • Work done = $ \frac{40}{75} = \frac{8}{15} $ of the total work.

Calculating Remaining Work

Determine the amount of work left after Lalit and Laxman have worked for $5$ days.

  • Total work = $1$ (representing the whole job).
  • Remaining work = $ 1 - \frac{8}{15} $.
  • Remaining work = $ \frac{15}{15} - \frac{8}{15} = \frac{7}{15} $ of the total work.

Finding Deven's Time

The remaining work ($ \frac{7}{15} $) is completed by Lalit and Deven in $4$ days. We need to find Deven's individual time.

  • Let Deven's time to finish the work alone be $D$ days.
  • Deven's work rate = $ \frac{1}{D} $ of the work per day.
  • Lalit's work rate is $ \frac{1}{15} $.
  • Combined work rate of Lalit and Deven = $ \frac{1}{15} + \frac{1}{D} $.
  • Work done by Lalit and Deven in $4$ days = $ \left(\frac{1}{15} + \frac{1}{D}\right) \times 4 $.
  • This equals the remaining work: $ \left(\frac{1}{15} + \frac{1}{D}\right) \times 4 = \frac{7}{15} $.
  • Distribute the $4$: $ \frac{4}{15} + \frac{4}{D} = \frac{7}{15} $.
  • Isolate the term with $D$: $ \frac{4}{D} = \frac{7}{15} - \frac{4}{15} $.
  • $ \frac{4}{D} = \frac{3}{15} = \frac{1}{5} $.
  • Solve for $D$: $ D = 4 \times 5 = 20 $.

Therefore, Deven can finish the work alone in $20\text{ days}$.

Was this answer helpful?

Similar Questions

  1. A contractor employs 15 men to complete a work in 24 days, working 8 hours per day. After six days, he adds five more men but also reduces the working hours to six per day from the seventh day onwards. If all men work with the same efficiency throughout, how many more days will be required to finish the remaining work?
  2. 6 women and 4 men can complete a work in 10 days, while 4 women and 5 men complete it in 10 days. In how many days will 8 women complete it?
  3. If 5 cats can catch 5 mice in 5 minutes, how many cats are needed to catch 100 mice in 100 min?
  4. A group of 5 men or 12 women can complete a task in 70 days. Find the time taken by 5 men and 12 women to complete the task.
  5. Athar can do a certain work in the same time in which Baban and Chetan together can do it. If Athar and Baban together could do it in 10 days and Chetan alone in 50 days, then Baban alone could do it in:
  6. 35 men can do a piece of work in 8 days. Find the time required by 16 men to do four times the work.
  7. Dhaval and Dhiraj together can do a piece of work in 12 days. Dhaval alone can do it in 20 days. In how many days can Dhiraj alone do it?
  8. 66 women can do a piece of work in 79 days. Find the number of days required by 6 women to complete 1 / 11th of the work.
  9. A, B, and C together can complete a task in 6 days. If A alone takes 12 days and B alone takes 18 days, how long will C alone take?
  10. A can complete a task in 15 days, and B can complete the same task in 20 days. How long will it take them to complete the task together?

Important Questions from Time and Work

  1. A and B can do a piece of work in 18 days. B and C together can do it in 30 days. If A is twice as good a workman as C, find in how many days B alone can do the work?

  2. Two men and 7 women can complete a work in 28 days, whereas 6 men and 16 women can do the same work in 11 days. In how many days will 5 men and 4 women, working together, complete the same work?

  3. A man and a woman, working together can do a work in 66 days. The ratio of their working efficiencies is 3 ∶ 2. In how many days 6 men and 2 women together can do the same work?

  4. Each one of five men independently can complete a work in 20 days. The work is started by one person. Next day one more person joins and every next day one more person joins. From the fifth day, five persons continued working as a team. In how many days, will the work be completed?

  5. Numan does half the work as Gagan in 4/5 of the time. If together they take 16 days to complete a piece of work, then how long will it take Gagan to complete the work?

Need Expert Advice?
Test Series
SSC CGL img
SSC
SSC CGL (Tier I + Tier II) 2026 Mock Test Series - Latest Pattern
1736 Tests 6 Tests Free
1855 Attempts
4.2(846)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App