0.05, 0.06, 0.05, 0.05, 0.05
0.06, 0.06, 0.05, 0.06, 0.06
What is the normal time for the element ?
The normal time for a work element is calculated by adjusting the average actual time observed by the performance rating given to the worker.
The formula used is:
$Normal Time = Average Actual Time × (Performance Rating / 100)$
First, find the average of the given actual time readings (in minutes).
Readings: 0.05, 0.06, 0.05, 0.05, 0.05, 0.06, 0.06, 0.05, 0.06, 0.06
Number of readings = 10
Sum of readings = $0.05 + 0.06 + 0.05 + 0.05 + 0.05 + 0.06 + 0.06 + 0.05 + 0.06 + 0.06 = 0.55$ minutes
Average Actual Time = $\frac{\text{Sum of readings}}{\text{Number of readings}} = \frac{0.55}{10} = 0.055$ minutes
Now, apply the performance rating (120%) to the average actual time.
Performance Rating = 120%
Normal Time = $0.055 \text{ minutes} \times \frac{120}{100}$
Normal Time = $0.055 \times 1.20$
Normal Time = $0.066$ minutes
Therefore, the normal time for the element is 0.066 minutes.
The situation of simultaneous satisfaction of row minima and column minima rule is termed as
Identify the correct combination of properties of point estimates form the options given below:
(a) Efficiency
(b) Consistency
(c) Adequacy
(d) Unbiasedness
Choose correct option:
In Operations management of an organization, the activities that assure the actual performance in accordance with planned performance are called:
Match the symbols used in preparation of process chart given in List - I with their description in List - II:
| List - I Symbols used in process chart | List - II Description |
|---|---|
| A. $\nabla$ | I. Movement from place to place |
| B. $\square$ | II. Delay |
| C. $\bigcirc$ | III. Inspection for quantity and quality |
D. ![]() | IV. Movement and Operation |
Choose the correct answer from the options given below :