0.05, 0.06, 0.05, 0.05, 0.05
0.06, 0.06, 0.05, 0.06, 0.06
What is the normal time for the element ?
The normal time for a work element is calculated by adjusting the average actual time observed by the performance rating given to the worker.
The formula used is:
$Normal Time = Average Actual Time × (Performance Rating / 100)$
First, find the average of the given actual time readings (in minutes).
Readings: 0.05, 0.06, 0.05, 0.05, 0.05, 0.06, 0.06, 0.05, 0.06, 0.06
Number of readings = 10
Sum of readings = $0.05 + 0.06 + 0.05 + 0.05 + 0.05 + 0.06 + 0.06 + 0.05 + 0.06 + 0.06 = 0.55$ minutes
Average Actual Time = $\frac{\text{Sum of readings}}{\text{Number of readings}} = \frac{0.55}{10} = 0.055$ minutes
Now, apply the performance rating (120%) to the average actual time.
Performance Rating = 120%
Normal Time = $0.055 \text{ minutes} \times \frac{120}{100}$
Normal Time = $0.055 \times 1.20$
Normal Time = $0.066$ minutes
Therefore, the normal time for the element is 0.066 minutes.
Match the symbols used in preparation of process chart given in List - I with their description in List - II:
| List - I Symbols used in process chart | List - II Description |
|---|---|
| A. $\nabla$ | I. Movement from place to place |
| B. $\square$ | II. Delay |
| C. $\bigcirc$ | III. Inspection for quantity and quality |
D. ![]() | IV. Movement and Operation |
Choose the correct answer from the options given below :
In Operations management of an organization, the activities that assure the actual performance in accordance with planned performance are called: