(a) Pasteurization
(b) Evaporation
(c) Milling
(d) Packing
(e) Clarification
(f) Fat seperation
(g) Roller drying
The manufacture of milk powder involves several key steps, each crucial for producing a safe, stable, and high-quality product. Arranging these processes in the correct operational order is essential.
Based on the standard manufacturing flow, the correct sequence of the given processes is:
Clarification (e) -> Fat Separation (f) -> Pasteurization (a) -> Evaporation (b) -> Roller Drying (g) -> Milling (c) -> Packing (d)
This corresponds to the order: (e), (f), (a), (b), (g), (c), (d).
The situation of simultaneous satisfaction of row minima and column minima rule is termed as
Identify the correct combination of properties of point estimates form the options given below:
(a) Efficiency
(b) Consistency
(c) Adequacy
(d) Unbiasedness
Choose correct option:
In Operations management of an organization, the activities that assure the actual performance in accordance with planned performance are called:
Match the symbols used in preparation of process chart given in List - I with their description in List - II:
| List - I Symbols used in process chart | List - II Description |
|---|---|
| A. $\nabla$ | I. Movement from place to place |
| B. $\square$ | II. Delay |
| C. $\bigcirc$ | III. Inspection for quantity and quality |
D. ![]() | IV. Movement and Operation |
Choose the correct answer from the options given below :