This problem involves calculating the time taken to complete a task (building a wall) when different entities work at different rates, and one entity stops working partway through. We need to understand the concept of work rates and how to combine them.
In problems like this, we often think about how much of the task can be completed in one unit of time (in this case, one hour).
Let's break down the problem into steps:
When the builder and the destroyer work together, the builder is building, and the destroyer is demolishing. So, their rates work against each other. The net rate at which the wall is being built is the builder's rate minus the destroyer's rate.
Combined Rate = Builder's Rate - Destroyer's Rate
Combined Rate = $ \frac{1}{10} - \frac{1}{20} $
To subtract these fractions, we find a common denominator, which is 20:
Combined Rate = $ \frac{2}{20} - \frac{1}{20} = \frac{1}{20} $ of the wall per hour.
This means that when they work together, $ \frac{1}{20} $ of the wall is built each hour.
Both the builder and the destroyer worked together for the first 15 hours. We can calculate how much of the wall was built during this time.
Work Done = Combined Rate $ \times $ Time Worked Together
Work Done = $ \frac{1}{20} \text{ wall/hour} \times 15 \text{ hours} $
Work Done = $ \frac{15}{20} = \frac{3}{4} $ of the wall.
So, after 15 hours, $ \frac{3}{4} $ of the wall was built.
The total work required is to build 1 complete wall. We need to find out how much work is left to be done.
Remaining Work = Total Work - Work Done
Remaining Work = $ 1 - \frac{3}{4} $
Remaining Work = $ \frac{1}{4} $ of the wall.
After 15 hours, the destroyer was withdrawn. The builder continued alone to finish the remaining $ \frac{1}{4} $ of the wall. We use the builder's individual rate for this calculation.
Time = Work / Rate
Time for Remaining Work = Remaining Work / Builder's Rate
Time for Remaining Work = $ \frac{1/4}{1/10} $ hours
Time for Remaining Work = $ \frac{1}{4} \times \frac{10}{1} = \frac{10}{4} = 2.5 $ hours.
The total time taken to build the wall is the sum of the time they worked together and the time the builder worked alone to finish the job.
Total Time = Time Worked Together + Time for Remaining Work
Total Time = $ 15 \text{ hours} + 2.5 \text{ hours} $
Total Time = $ 17.5 $ hours.
The total time taken to build the wall was 17.5 hours.
Three pipes A, B and C can fill a tank in $10$, $15$ and $20$ hours respectively. Pipe A was opened at $6$ AM, pipe B at $7$ AM and pipe C at $8$ AM. At what time was the tank completely filled, if pipe C needs a break of $1$ hour after remaining open for $3$ hours?
A tank has four pipes $P_1$, $P_2$, $P_3$ and $P_4$. The tank can be filled in $15$ minutes by pipes $P_1$, $P_2$, $P_3$ together. It can be filled in $20$ minutes by pipes $P_2$, $P_3$, $P_4$ together and it can be filled by pipes $P_1$, $P_4$ together in $30$ minutes. If all the pipes are opened together, then in how much time will the tank be filled?
$5$ men and $4$ women can earn ₹ $20000$ in $8$ days. $10$ men and $7$ women can earn ₹ $23,750$ in $5$ days. In how many days will $5$ men and $6$ women earn ₹ $12,000$?