This problem involves calculating the time taken to complete a task (building a wall) based on the rates of work of different entities. In this scenario, we have a builder who constructs the wall and a destroyer who demolishes it.
Initially, both the builder and the destroyer work together for 15 hours. To find their combined effect, we subtract the destroyer's rate from the builder's rate:
Builder's Rate ($R_B$) = $\frac{1}{10}$ wall/hour
Destroyer's Rate ($R_D$) = $\frac{1}{20}$ wall/hour
Combined Rate ($R_{Combined}$) = $R_B - R_D$
Using LaTeX for the calculation:
$R_{Combined} = \frac{1}{10} - \frac{1}{20}$
To subtract these fractions, we find a common denominator, which is 20:
$R_{Combined} = \frac{2}{20} - \frac{1}{20} = \frac{1}{20}$
So, when working together, they build $\frac{1}{20}$ of the wall every hour.
They work together for 15 hours. The amount of wall built during this time is:
Work Done = Combined Rate $\times$ Time
Work Done = $\frac{1}{20}$ wall/hour $\times 15$ hours
$ \text{Work Done} = \frac{15}{20} = \frac{3}{4} $
After 15 hours, $\frac{3}{4}$ of the wall is built.
After 15 hours, the destroyer is withdrawn. The remaining portion of the wall that needs to be built is:
Remaining Work = Total Work - Work Done
Remaining Work = $1 - \frac{3}{4}$
$ \text{Remaining Work} = \frac{1}{4} $
Now, only the builder works to complete the remaining $\frac{1}{4}$ of the wall. The builder's rate is $\frac{1}{10}$ wall per hour.
Time taken by builder = $\frac{\text{Remaining Work}}{\text{Builder's Rate}}$
Time taken by builder = $\frac{1/4}{1/10}$ hours
$ \text{Time taken by builder} = \frac{1}{4} \times \frac{10}{1} = \frac{10}{4} = 2.5 \text{ hours} $
The total time taken to build the wall is the sum of the time they worked together and the time the builder took to finish the remaining part.
Total Time = Time Worked Together + Time Builder Worked Alone
Total Time = 15 hours + 2.5 hours
Total Time = 17.5 hours
Therefore, the total time taken to build the wall is 17.5 hours.
Aman can do 50% of the job in 16 days, and Bhanu can do 25% of the job in 24 days. In how many days can they do $\frac{1}{4}^{th}$ of the job working together ?
Ravina, Sujata, and Saroj can complete a work of painting separately in 32, 48, and 64 hours, respectively. They started working together, but Saroj left after 5 hours. From the 6th hour, Ravina and Sujata decided to work on alternate hours starting with Ravina. In how much time will the entire work of painting be completed?