All Exams Test series for 1 year @ ₹349 only
Question

If 15 workers can build a wall in 10 days, how many workers are needed to build it in 6 days?

The correct answer is
25

Work and Time Calculation

This problem involves an inverse relationship between the number of workers and the time taken to complete a job. If the time decreases, the number of workers must increase proportionally.

Calculating Total Work

The total amount of work required to build the wall is constant. We can calculate it by multiplying the initial number of workers by the time they took.

Total Work = (Number of Workers) \times (Number of Days)

Total Work = 15 \text{ workers} \times 10 \text{ days} = 150 \text{ worker-days}

Determining Workers Needed

Now, we need to find out how many workers are needed to complete the same 150 worker-days of work in just 6 days.

Let the required number of workers be 'W'.

W \times 6 \text{ days} = 150 \text{ worker-days}

To find W, we rearrange the equation:

W = \frac{150 \text{ worker-days}}{6 \text{ days}}

W = 25 \text{ workers}

Conclusion

Therefore, 25 workers are needed to build the wall in 6 days.

Was this answer helpful?

Important Questions from Time & Work (Notes)

  1. Aman can do 50% of the job in 16 days, and Bhanu can do 25% of the job in 24 days. In how many days can they do $\frac{1}{4}^{th}$  of the job working together ?

  2. X can finish a job in $141$ days. He worked for $57$ days alone and the remaining work was completed by Y, in $84$ days. How many days would both together take to complete the entire job?
  3. Ravina, Sujata, and Saroj can complete a work of painting separately in 32, 48, and 64 hours, respectively. They started working together, but Saroj left after 5 hours. From the 6th hour, Ravina and Sujata decided to work on alternate hours starting with Ravina. In how much time will the entire work of painting be completed?

  4. A and B complete a work in 6 days. If A alone can do it in 9 days, then B alone can do $\frac{1}{3}$ of the same work in ________ (days).

  5. A construction project requires 18 workers working for 25 days. After 10 days, 6 workers leave and 4 new workers join who are 25% more efficient than original workers. After 5 more days, all remaining workers increase their efficiency by 20%. How many total days will the project take to complete?
Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App