If 15 workers can build a 1500 m long road in 25 days, working 8 hours a day, how many days will 16 workers take to build a 2400 m long road, working 6 hours a day?
50 days
Use the work formula: (M₁ × D₁ × H₁)/W₁ = (M₂ × D₂ × H₂)/W₂
(15 × 25 × 8)/1500 = (16 × D × 6)/2400
3000/1500 = 96D/2400
2 = 96D/2400
D = 4800/96
= 50 days
Check: 16 × 50 × 6 = 4800 worker-hours for 2400 m gives 2 worker-hours per metre, same as 3000 for 1500 m.
Hence, 50 days.
A can complete a piece of work in 10 days, and B can do the same work in 15 days. They work together for 5 days, and then C finishes the remaining work in 2 days. How long would C alone take to complete the entire work?
If 12 workers can build a wall in 15 days, working 6 hours per day, then in how many days can 10 workers build two such walls, if they work for 4 hours per day?
A person can complete 20% of work in 8 days and another person y can complete 25% of the same work in 6 days. If they work together, in how many days will 40% of the work be completed?
P works thrice as fast as Q, whereas P and Q together can work four times as fast as R. If P, Q and R together work on a job, in what ratio should they share the earnings?
There are three pillars X, Y and Z of different heights. Three spiders A, B and C start to climb on these pillars simultaneously. In one chance, A climbs on X by 6 cm but slips down 1 cm. B climbs on Y by 7 cm but slips down 3 cm. C climbs on Z by 6.5 cm but slips down 2 cm. If each of them requires 40 chances to reach the top of the pillars, what is the height of the shortest pillar?
There is an order of 19000 quantity of a particular product from a customer. The firm produces 1000 quantity of that product per out of which 5% are unfit for sale. In how many days will the order be completed?
Ram and Shyam work on a job together for four days and complete 60% of it. Ram takes leave then and Shyam works for eight more days to complete the job. How long would Ram take to complete the entire job alone?