A can complete a piece of work in 10 days, and B can do the same work in 15 days. They work together for 5 days, and then C finishes the remaining work in 2 days. How long would C alone take to complete the entire work?

The correct answer is

12 days

One day's work of A = \(\frac{1}{10}\) and of B = \(\frac{1}{15}\); together = \(\frac{1}{10} + \frac{1}{15} = \frac{5}{30} = \frac{1}{6}\).

Work done by A and B in 5 days = \(5 \times \frac{1}{6} = \frac{5}{6}\), so remaining work = \(\frac{1}{6}\).

C does \(\frac{1}{6}\) of the work in 2 days, so C alone does the whole work in \(2 \times 6 = 12\) days.

Hence, the answer is 12 days.

Was this answer helpful?

Similar Questions

  1. If 12 workers can build a wall in 15 days, working 6 hours per day, then in how many days can 10 workers build two such walls, if they work for 4 hours per day?

  2. If 15 workers can build a 1500 m long road in 25 days, working 8 hours a day, how many days will 16 workers take to build a 2400 m long road, working 6 hours a day?


Important Questions from Time and work

  1. A person can complete 20% of work in 8 days and another person y can complete 25% of the same work in 6 days. If they work together, in how many days will 40% of the work be completed?

  2. P works thrice as fast as Q, whereas P and Q together can work four times as fast as R. If P, Q and R together work on a job, in what ratio should they share the earnings?

  3. There are three pillars X, Y and Z of different heights. Three spiders A, B and C start to climb on these pillars simultaneously. In one chance, A climbs on X by 6 cm but slips down 1 cm. B climbs on Y by 7 cm but slips down 3 cm. C climbs on Z by 6.5 cm but slips down 2 cm. If each of them requires 40 chances to reach the top of the pillars, what is the height of the shortest pillar?

  4. There is an order of 19000 quantity of a particular product from a customer. The firm produces 1000 quantity of that product per out of which 5% are unfit for sale. In how many days will the order be completed?

  5. Ram and Shyam work on a job together for four days and complete 60% of it. Ram takes leave then and Shyam works for eight more days to complete the job. How long would Ram take to complete the entire job alone?

Need Expert Advice?
Test Series
AFCAT img
Defence
AFCAT 01/2027 Mock Test Series
460 Tests
4.4(29)
English
More Questions from AFCAT

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App