A can complete a piece of work in 10 days, and B can do the same work in 15 days. They work together for 5 days, and then C finishes the remaining work in 2 days. How long would C alone take to complete the entire work?
12 days
One day's work of A = \(\frac{1}{10}\) and of B = \(\frac{1}{15}\); together = \(\frac{1}{10} + \frac{1}{15} = \frac{5}{30} = \frac{1}{6}\).
Work done by A and B in 5 days = \(5 \times \frac{1}{6} = \frac{5}{6}\), so remaining work = \(\frac{1}{6}\).
C does \(\frac{1}{6}\) of the work in 2 days, so C alone does the whole work in \(2 \times 6 = 12\) days.
Hence, the answer is 12 days.
If 12 workers can build a wall in 15 days, working 6 hours per day, then in how many days can 10 workers build two such walls, if they work for 4 hours per day?
If 15 workers can build a 1500 m long road in 25 days, working 8 hours a day, how many days will 16 workers take to build a 2400 m long road, working 6 hours a day?
A can lay railway track between two given stations in 17 days and B can do the same job in 16 days. With the help of C, they did the job in 4 days only. Then, C alone can do the job in __________