If 12 workers can build a wall in 15 days, working 6 hours per day, then in how many days can 10 workers build two such walls, if they work for 4 hours per day?
54 days
Use \(\frac{M_1 D_1 H_1}{W_1}=\frac{M_2 D_2 H_2}{W_2}\), where M = workers, D = days, H = hours per day and W = work.
Work in one wall: \(12\times15\times6=1080\) worker-hours. Two walls need \(2\times1080=2160\) worker-hours.
With 10 workers at 4 hours per day: \(D_2=\frac{2160}{10\times4}=54\) days.
Hence, the answer is 54 days.
A can complete a piece of work in 10 days, and B can do the same work in 15 days. They work together for 5 days, and then C finishes the remaining work in 2 days. How long would C alone take to complete the entire work?
If 15 workers can build a 1500 m long road in 25 days, working 8 hours a day, how many days will 16 workers take to build a 2400 m long road, working 6 hours a day?
A can lay railway track between two given stations in 17 days and B can do the same job in 16 days. With the help of C, they did the job in 4 days only. Then, C alone can do the job in __________